{"title":"一种新的高效并行机器作业调度优先级规则","authors":"Nabil Sahraoui, H. Hentous","doi":"10.1109/ICMWI.2010.5647922","DOIUrl":null,"url":null,"abstract":"This article aims to study the problem of scheduling on identical parallel machines with different release dates and precedence constraints in tree form to minimize the number of the late jobs; this particular criterion is often used like a performance indicator. This problem is noted by Pm| ri, outtree|∑Ui in standard classification (Graham and Al, 1979). Initially, we present an outline of the work completed by the problems of scheduling to minimize the number of the late jobs. Thereafter we propose two heuristics to solve this problem, the first heuristic based on a new priority rule and the second based on EDD rule.","PeriodicalId":404577,"journal":{"name":"2010 International Conference on Machine and Web Intelligence","volume":"29 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2010-11-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"A new efficient priority rule for scheduling job on identical parallel machines\",\"authors\":\"Nabil Sahraoui, H. Hentous\",\"doi\":\"10.1109/ICMWI.2010.5647922\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This article aims to study the problem of scheduling on identical parallel machines with different release dates and precedence constraints in tree form to minimize the number of the late jobs; this particular criterion is often used like a performance indicator. This problem is noted by Pm| ri, outtree|∑Ui in standard classification (Graham and Al, 1979). Initially, we present an outline of the work completed by the problems of scheduling to minimize the number of the late jobs. Thereafter we propose two heuristics to solve this problem, the first heuristic based on a new priority rule and the second based on EDD rule.\",\"PeriodicalId\":404577,\"journal\":{\"name\":\"2010 International Conference on Machine and Web Intelligence\",\"volume\":\"29 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2010-11-29\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2010 International Conference on Machine and Web Intelligence\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICMWI.2010.5647922\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2010 International Conference on Machine and Web Intelligence","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICMWI.2010.5647922","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
本文研究了具有不同放行日期和优先级约束的同一并行机器的树形调度问题,以最小化延迟作业的数量;这个特定的标准通常用作性能指标。标准分类中的Pm| ri, outtree|∑Ui注意到了这个问题(Graham and Al, 1979)。首先,我们提出了一个由调度问题完成的工作大纲,以尽量减少延迟作业的数量。在此基础上,我们提出了两种启发式算法来解决这个问题,第一种是基于新的优先级规则的启发式算法,第二种是基于EDD规则的启发式算法。
A new efficient priority rule for scheduling job on identical parallel machines
This article aims to study the problem of scheduling on identical parallel machines with different release dates and precedence constraints in tree form to minimize the number of the late jobs; this particular criterion is often used like a performance indicator. This problem is noted by Pm| ri, outtree|∑Ui in standard classification (Graham and Al, 1979). Initially, we present an outline of the work completed by the problems of scheduling to minimize the number of the late jobs. Thereafter we propose two heuristics to solve this problem, the first heuristic based on a new priority rule and the second based on EDD rule.