{"title":"环境审批条件是否有助落实最佳环评措施,从而加强环评制度?印度案例研究分析","authors":"A. Rathi","doi":"10.30564/mmpp.v4i2.4729","DOIUrl":null,"url":null,"abstract":"The environmental approval for a project is generally granted with a set of terms and conditions to the project proponent. The environmental clearance (EC) letters for 33 infrastructure projects were examined for the relevance, adequacy, and enforceability of the EC conditions. Using the basic tenets of the EIA process, it is found that the long list of irrelevant, inadequate, and unenforceable conditions is greenwash and unsuited for best practice EIA follow-up, hence meeting the EIA objectives. The conditions should be directed at measuring the environmental performance of the project to catalyze achieving sustainability targets. The conditions for stringent supervision and frequent inspection of the site activities in the construction phase could help ensure the implementation of the proposed mitigation measures for infrastructure projects. A comprehensive environmental impact assessment framework may use the principles of the ABC analysis to prioritize the properly specified EC conditions, resource allocation, and stakeholder engagement for the best practice EIA follow-up and hence strengthen the EIA system.","PeriodicalId":402578,"journal":{"name":"Macro Management & Public Policies","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-07-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Do the Environmental Approval Conditions Enable the Best Practice EIA Follow-up and Hence Strengthen the EIA System? An Indian Case Study Analysis\",\"authors\":\"A. Rathi\",\"doi\":\"10.30564/mmpp.v4i2.4729\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The environmental approval for a project is generally granted with a set of terms and conditions to the project proponent. The environmental clearance (EC) letters for 33 infrastructure projects were examined for the relevance, adequacy, and enforceability of the EC conditions. Using the basic tenets of the EIA process, it is found that the long list of irrelevant, inadequate, and unenforceable conditions is greenwash and unsuited for best practice EIA follow-up, hence meeting the EIA objectives. The conditions should be directed at measuring the environmental performance of the project to catalyze achieving sustainability targets. The conditions for stringent supervision and frequent inspection of the site activities in the construction phase could help ensure the implementation of the proposed mitigation measures for infrastructure projects. A comprehensive environmental impact assessment framework may use the principles of the ABC analysis to prioritize the properly specified EC conditions, resource allocation, and stakeholder engagement for the best practice EIA follow-up and hence strengthen the EIA system.\",\"PeriodicalId\":402578,\"journal\":{\"name\":\"Macro Management & Public Policies\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-07-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Macro Management & Public Policies\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.30564/mmpp.v4i2.4729\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Macro Management & Public Policies","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30564/mmpp.v4i2.4729","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

工程项目的环境审批一般会向工程项目的倡议者提供一套条款和条件。对33个基础设施项目的环境许可函进行了审查,以确定环境许可条件的相关性、充分性和可执行性。根据环评程序的基本原则,我们发现一长串不相关、不充分和无法执行的条件是粉饰事实,不适合进行环评跟进的最佳做法,因此不符合环评目标。这些条件应用于衡量项目的环境绩效,以促进实现可持续性目标。在施工阶段严格监督和经常检查工地活动的条件,有助于确保拟议的基础设施项目缓解措施得到实施。一个全面的环境影响评估框架可以利用作业成本法分析的原则,优先考虑适当指定的环境影响评估条件、资源分配和利益相关者参与,以便进行最佳的环境影响评估跟进工作,从而加强环境影响评估系统。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Do the Environmental Approval Conditions Enable the Best Practice EIA Follow-up and Hence Strengthen the EIA System? An Indian Case Study Analysis
The environmental approval for a project is generally granted with a set of terms and conditions to the project proponent. The environmental clearance (EC) letters for 33 infrastructure projects were examined for the relevance, adequacy, and enforceability of the EC conditions. Using the basic tenets of the EIA process, it is found that the long list of irrelevant, inadequate, and unenforceable conditions is greenwash and unsuited for best practice EIA follow-up, hence meeting the EIA objectives. The conditions should be directed at measuring the environmental performance of the project to catalyze achieving sustainability targets. The conditions for stringent supervision and frequent inspection of the site activities in the construction phase could help ensure the implementation of the proposed mitigation measures for infrastructure projects. A comprehensive environmental impact assessment framework may use the principles of the ABC analysis to prioritize the properly specified EC conditions, resource allocation, and stakeholder engagement for the best practice EIA follow-up and hence strengthen the EIA system.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信