太阳能光伏能源变压器使用寿命成本的进一步探讨

B. A. Thango, K. Moloi, J. Jordaan, A. F. Nnnach
{"title":"太阳能光伏能源变压器使用寿命成本的进一步探讨","authors":"B. A. Thango, K. Moloi, J. Jordaan, A. F. Nnnach","doi":"10.1109/SAUPEC/RobMech/PRASA52254.2021.9377229","DOIUrl":null,"url":null,"abstract":"In this day and age, there is a proliferate concern from all governments across the globe to barricade the environment from the greenhouse gases, which absorb infrared radiation. As a result, solar photovoltaic (PV) energy has been an expeditiously growing renewable energy source and will eventually undertake a prominent role in the global energy generation. The selection and purchasing of energy efficient transformers which meet the operational requirements of the solar photovoltaic energy generation plants then becomes a part of the Independent Power Producers (IPP’s) investment plan of action. Taking these into account, this work proposes a novel procedure that put into effect the intricate financial analysis necessitated to precisely evaluate the transformer service lifetime no-load and load loss factors. This procedure correctly set forth the transformer service lifetime loss factors as a result of solar PV plant’s sporadic generation profile and related levelized costs of electricity into the computation of the transformer’s total ownership cost. The results are then critically compared with the conventional transformer total ownership cost (TCO), and demonstrate the significance of the sporadic energy generation nature of the solar PV plant on the total ownership cost. The findings indicate that the latter play a crucial role for developers and Independent Power Producers (IPP’s) in making the purchase decision during a tender bid where competing offers from different transformer manufactures are evaluated. Additionally, the susceptibility analysis of different factors engrossed in the transformer service lifetime cost is carried out, factors including the levelized cost of electricity, solar PV plant’s generation modes and the loading profile are examined.","PeriodicalId":442944,"journal":{"name":"2021 Southern African Universities Power Engineering Conference/Robotics and Mechatronics/Pattern Recognition Association of South Africa (SAUPEC/RobMech/PRASA)","volume":"72 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-01-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"A Further Look into the Service Lifetime Cost of Solar Photovoltaic Energy Transformers\",\"authors\":\"B. A. Thango, K. Moloi, J. Jordaan, A. F. Nnnach\",\"doi\":\"10.1109/SAUPEC/RobMech/PRASA52254.2021.9377229\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In this day and age, there is a proliferate concern from all governments across the globe to barricade the environment from the greenhouse gases, which absorb infrared radiation. As a result, solar photovoltaic (PV) energy has been an expeditiously growing renewable energy source and will eventually undertake a prominent role in the global energy generation. The selection and purchasing of energy efficient transformers which meet the operational requirements of the solar photovoltaic energy generation plants then becomes a part of the Independent Power Producers (IPP’s) investment plan of action. Taking these into account, this work proposes a novel procedure that put into effect the intricate financial analysis necessitated to precisely evaluate the transformer service lifetime no-load and load loss factors. This procedure correctly set forth the transformer service lifetime loss factors as a result of solar PV plant’s sporadic generation profile and related levelized costs of electricity into the computation of the transformer’s total ownership cost. The results are then critically compared with the conventional transformer total ownership cost (TCO), and demonstrate the significance of the sporadic energy generation nature of the solar PV plant on the total ownership cost. The findings indicate that the latter play a crucial role for developers and Independent Power Producers (IPP’s) in making the purchase decision during a tender bid where competing offers from different transformer manufactures are evaluated. Additionally, the susceptibility analysis of different factors engrossed in the transformer service lifetime cost is carried out, factors including the levelized cost of electricity, solar PV plant’s generation modes and the loading profile are examined.\",\"PeriodicalId\":442944,\"journal\":{\"name\":\"2021 Southern African Universities Power Engineering Conference/Robotics and Mechatronics/Pattern Recognition Association of South Africa (SAUPEC/RobMech/PRASA)\",\"volume\":\"72 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-01-27\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2021 Southern African Universities Power Engineering Conference/Robotics and Mechatronics/Pattern Recognition Association of South Africa (SAUPEC/RobMech/PRASA)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/SAUPEC/RobMech/PRASA52254.2021.9377229\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2021 Southern African Universities Power Engineering Conference/Robotics and Mechatronics/Pattern Recognition Association of South Africa (SAUPEC/RobMech/PRASA)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/SAUPEC/RobMech/PRASA52254.2021.9377229","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

摘要

在这个时代,全球各国政府越来越关注如何使环境免受吸收红外辐射的温室气体的影响。因此,太阳能光伏(PV)能源已成为一种快速增长的可再生能源,并最终将在全球能源生产中发挥突出作用。选择和购买符合太阳能光伏发电厂运行要求的节能变压器,成为独立电力生产商(IPP)投资行动计划的一部分。考虑到这些因素,本工作提出了一种新的程序,该程序实现了精确评估变压器使用寿命空载和负载损耗因素所需的复杂财务分析。该程序正确地将太阳能光伏电站的零星发电情况和相关的平准化电力成本导致的变压器使用寿命损失因素纳入变压器总拥有成本的计算中。然后将结果与传统变压器总拥有成本(TCO)进行了严格比较,并证明了太阳能光伏电站的零星发电性质对总拥有成本的重要性。研究结果表明,在评估来自不同变压器制造商的竞争报价的投标过程中,后者对开发商和独立电力生产商(IPP)做出购买决策起着至关重要的作用。此外,还对影响变压器寿命成本的因素进行了敏感性分析,考察了电力平准化成本、太阳能光伏电站发电方式和负荷分布等因素。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
A Further Look into the Service Lifetime Cost of Solar Photovoltaic Energy Transformers
In this day and age, there is a proliferate concern from all governments across the globe to barricade the environment from the greenhouse gases, which absorb infrared radiation. As a result, solar photovoltaic (PV) energy has been an expeditiously growing renewable energy source and will eventually undertake a prominent role in the global energy generation. The selection and purchasing of energy efficient transformers which meet the operational requirements of the solar photovoltaic energy generation plants then becomes a part of the Independent Power Producers (IPP’s) investment plan of action. Taking these into account, this work proposes a novel procedure that put into effect the intricate financial analysis necessitated to precisely evaluate the transformer service lifetime no-load and load loss factors. This procedure correctly set forth the transformer service lifetime loss factors as a result of solar PV plant’s sporadic generation profile and related levelized costs of electricity into the computation of the transformer’s total ownership cost. The results are then critically compared with the conventional transformer total ownership cost (TCO), and demonstrate the significance of the sporadic energy generation nature of the solar PV plant on the total ownership cost. The findings indicate that the latter play a crucial role for developers and Independent Power Producers (IPP’s) in making the purchase decision during a tender bid where competing offers from different transformer manufactures are evaluated. Additionally, the susceptibility analysis of different factors engrossed in the transformer service lifetime cost is carried out, factors including the levelized cost of electricity, solar PV plant’s generation modes and the loading profile are examined.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信