基于追踪法的轮转储备成本分摊

Yusuf Susilo Wijoyo, Sasongko Pramono Hadi, S. Sarjiya
{"title":"基于追踪法的轮转储备成本分摊","authors":"Yusuf Susilo Wijoyo, Sasongko Pramono Hadi, S. Sarjiya","doi":"10.1109/ICITEE49829.2020.9271724","DOIUrl":null,"url":null,"abstract":"Renewable energy has site-specific characteristics and uncertainty in its production. The location of large-scale renewable energy generators, which are generally far from the load location, requires the construction of a transmission network which is relatively difficult to build. Fluctuating production causes the need for backup supplies. These site-specific characteristics and uncertainty problems are opportunities for utility to provide wheeling and reserve services. This reserve service creates additional costs for system operation that must be added to wheeling costs as a component of the reserve cost. The research was conducted on a modified IEEE 30 bus system. The impact of not producing wheeling generators on utility operating costs was observed with optimal power flow. The impact obtained is then allocated to the wheeling entity using the tracing method, which in this study consists of two entities. The calculation results show an increase in utility operating costs by 115.13 $/hr when the wheeling generator is not producing. The first wheeling entity bears costs of 23.20 $/hr and the second wheeling entity bears 91.93 $/hr.","PeriodicalId":245013,"journal":{"name":"2020 12th International Conference on Information Technology and Electrical Engineering (ICITEE)","volume":"52 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-10-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Reserve Cost Allocation on Wheeling Using Tracing Method\",\"authors\":\"Yusuf Susilo Wijoyo, Sasongko Pramono Hadi, S. Sarjiya\",\"doi\":\"10.1109/ICITEE49829.2020.9271724\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Renewable energy has site-specific characteristics and uncertainty in its production. The location of large-scale renewable energy generators, which are generally far from the load location, requires the construction of a transmission network which is relatively difficult to build. Fluctuating production causes the need for backup supplies. These site-specific characteristics and uncertainty problems are opportunities for utility to provide wheeling and reserve services. This reserve service creates additional costs for system operation that must be added to wheeling costs as a component of the reserve cost. The research was conducted on a modified IEEE 30 bus system. The impact of not producing wheeling generators on utility operating costs was observed with optimal power flow. The impact obtained is then allocated to the wheeling entity using the tracing method, which in this study consists of two entities. The calculation results show an increase in utility operating costs by 115.13 $/hr when the wheeling generator is not producing. The first wheeling entity bears costs of 23.20 $/hr and the second wheeling entity bears 91.93 $/hr.\",\"PeriodicalId\":245013,\"journal\":{\"name\":\"2020 12th International Conference on Information Technology and Electrical Engineering (ICITEE)\",\"volume\":\"52 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2020-10-06\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2020 12th International Conference on Information Technology and Electrical Engineering (ICITEE)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICITEE49829.2020.9271724\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2020 12th International Conference on Information Technology and Electrical Engineering (ICITEE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICITEE49829.2020.9271724","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

可再生能源具有区位特征和生产的不确定性。大型可再生能源发电机的选址一般离负荷位置较远,需要建设输电网络,建设难度较大。生产波动导致需要备用供应。这些特定场地的特点和不确定性问题是公用事业公司提供轮转和备用服务的机会。这种备用服务增加了系统运行的额外成本,必须作为备用成本的组成部分添加到轮转成本中。研究是在一个改进的IEEE 30总线系统上进行的。在最优潮流下,观察了不生产轮式发电机对公用事业运行成本的影响。然后使用跟踪方法将获得的冲击分配给车轮实体,在本研究中车轮实体由两个实体组成。计算结果表明,当轮式发电机不发电时,公用事业运行成本增加115.13美元/小时。第一轮实体承担的成本为23.20美元/小时,第二轮实体承担的成本为91.93美元/小时。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Reserve Cost Allocation on Wheeling Using Tracing Method
Renewable energy has site-specific characteristics and uncertainty in its production. The location of large-scale renewable energy generators, which are generally far from the load location, requires the construction of a transmission network which is relatively difficult to build. Fluctuating production causes the need for backup supplies. These site-specific characteristics and uncertainty problems are opportunities for utility to provide wheeling and reserve services. This reserve service creates additional costs for system operation that must be added to wheeling costs as a component of the reserve cost. The research was conducted on a modified IEEE 30 bus system. The impact of not producing wheeling generators on utility operating costs was observed with optimal power flow. The impact obtained is then allocated to the wheeling entity using the tracing method, which in this study consists of two entities. The calculation results show an increase in utility operating costs by 115.13 $/hr when the wheeling generator is not producing. The first wheeling entity bears costs of 23.20 $/hr and the second wheeling entity bears 91.93 $/hr.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信