反映韩国公共建设工程特点的综合工程造价管理方法研究

Seong-Jin Kim, Tae-Hak Kim
{"title":"反映韩国公共建设工程特点的综合工程造价管理方法研究","authors":"Seong-Jin Kim, Tae-Hak Kim","doi":"10.1109/CSCESM.2015.7331831","DOIUrl":null,"url":null,"abstract":"Given their nature, construction projects should consider various factors such as the budget, period, methods, various participants under different construction environments, massive manpower, materials, and equipment so that they can be completed according to the given timeline and within the given budget. They also require a huge budget, thereby calling for an integrated systematic management system designed to ensure accurate performance measurement and analysis and to forecast the final construction cost. To effectively apply the earned-value management system (EVMS) to public construction projects, this study examined EVMS theories, derived EVMS problems, and developed and presented the display screens for the integrated process and construction cost management system suitable for public construction projects.","PeriodicalId":232149,"journal":{"name":"2015 Second International Conference on Computer Science, Computer Engineering, and Social Media (CSCESM)","volume":"19 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2015-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"A study on the integrated construction cost management method with reflection of the characteristics of public construction works in South Korea\",\"authors\":\"Seong-Jin Kim, Tae-Hak Kim\",\"doi\":\"10.1109/CSCESM.2015.7331831\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Given their nature, construction projects should consider various factors such as the budget, period, methods, various participants under different construction environments, massive manpower, materials, and equipment so that they can be completed according to the given timeline and within the given budget. They also require a huge budget, thereby calling for an integrated systematic management system designed to ensure accurate performance measurement and analysis and to forecast the final construction cost. To effectively apply the earned-value management system (EVMS) to public construction projects, this study examined EVMS theories, derived EVMS problems, and developed and presented the display screens for the integrated process and construction cost management system suitable for public construction projects.\",\"PeriodicalId\":232149,\"journal\":{\"name\":\"2015 Second International Conference on Computer Science, Computer Engineering, and Social Media (CSCESM)\",\"volume\":\"19 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2015-09-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2015 Second International Conference on Computer Science, Computer Engineering, and Social Media (CSCESM)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/CSCESM.2015.7331831\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2015 Second International Conference on Computer Science, Computer Engineering, and Social Media (CSCESM)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/CSCESM.2015.7331831","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

由于其性质,建设项目需要考虑预算、工期、方法、不同施工环境下的不同参与者、大量的人力、材料和设备等因素,才能在规定的时间内、在规定的预算范围内完成。它们还需要巨大的预算,因此需要一个综合系统的管理系统,旨在确保准确的绩效测量和分析,并预测最终的建设成本。为了有效地将挣值管理系统(EVMS)应用到公共建设项目中,本研究考察了EVMS理论,推导了EVMS存在的问题,开发并提出了适合公共建设项目的综合流程与工程造价管理系统的展示画面。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
A study on the integrated construction cost management method with reflection of the characteristics of public construction works in South Korea
Given their nature, construction projects should consider various factors such as the budget, period, methods, various participants under different construction environments, massive manpower, materials, and equipment so that they can be completed according to the given timeline and within the given budget. They also require a huge budget, thereby calling for an integrated systematic management system designed to ensure accurate performance measurement and analysis and to forecast the final construction cost. To effectively apply the earned-value management system (EVMS) to public construction projects, this study examined EVMS theories, derived EVMS problems, and developed and presented the display screens for the integrated process and construction cost management system suitable for public construction projects.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信