{"title":"基于挣值法的Kebayoran Sarana Loka Almika PT Griya Jenggala开发项目控制分析","authors":"Heni Nastiti, Denta Sawwath Suryana, Fattan Rahmat Firza Aulia, Muhammad Rayhan Ramsyahdira","doi":"10.28932/ice.v4i3.7346","DOIUrl":null,"url":null,"abstract":"Project control is a structured effort to establish standards in accordance with the plan, design information systems, compare implementation with established standards, analyze potential deviations, and take corrective actions necessary to ensure the effective and efficient use of resources in line with the set targets. Each project has its own specific plan and schedule, determining the start and end time of the project, implementation methods, and resource allocation. Operational challenges often arise in project planning, such as resource shortages, improper allocation, delays, and other issues that may hinder the achievement of project goals as planned. This research utilizes a descriptive quantitative approach, which is a research method that describes the specific conditions of the project through the analysis of available data. This article will discuss the cost variance (CV) and schedule variance (SV) in the development of Griya Jenggala at PT. Sarana Loka Almika, evaluate the cost performance index (CPI) and schedule performance index (SPI) in the development of Griya Jenggala to assess its effectiveness, estimate the cost at completion (EAC) and estimated duration at completion (EAS) required to complete the Griya Jenggala project, as well as provide an estimation of potential profits or losses that may arise in the Griya Jenggala development project.","PeriodicalId":193086,"journal":{"name":"Journal of Innovation and Community Engagement","volume":"42 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-08-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Control Analysis of the Griya Jenggala Development Project using the Earned Value Method at PT Sarana Loka Almika in Kebayoran\",\"authors\":\"Heni Nastiti, Denta Sawwath Suryana, Fattan Rahmat Firza Aulia, Muhammad Rayhan Ramsyahdira\",\"doi\":\"10.28932/ice.v4i3.7346\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Project control is a structured effort to establish standards in accordance with the plan, design information systems, compare implementation with established standards, analyze potential deviations, and take corrective actions necessary to ensure the effective and efficient use of resources in line with the set targets. Each project has its own specific plan and schedule, determining the start and end time of the project, implementation methods, and resource allocation. Operational challenges often arise in project planning, such as resource shortages, improper allocation, delays, and other issues that may hinder the achievement of project goals as planned. This research utilizes a descriptive quantitative approach, which is a research method that describes the specific conditions of the project through the analysis of available data. This article will discuss the cost variance (CV) and schedule variance (SV) in the development of Griya Jenggala at PT. Sarana Loka Almika, evaluate the cost performance index (CPI) and schedule performance index (SPI) in the development of Griya Jenggala to assess its effectiveness, estimate the cost at completion (EAC) and estimated duration at completion (EAS) required to complete the Griya Jenggala project, as well as provide an estimation of potential profits or losses that may arise in the Griya Jenggala development project.\",\"PeriodicalId\":193086,\"journal\":{\"name\":\"Journal of Innovation and Community Engagement\",\"volume\":\"42 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-08-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Innovation and Community Engagement\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.28932/ice.v4i3.7346\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Innovation and Community Engagement","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.28932/ice.v4i3.7346","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
项目控制是根据计划建立标准,设计信息系统,比较实施与建立的标准,分析潜在的偏差,并采取必要的纠正措施,以确保有效和高效地使用资源,符合设定的目标。每个项目都有自己的具体计划和时间表,确定了项目的开始和结束时间、实施方法和资源分配。在项目计划中经常出现操作性挑战,例如资源短缺、分配不当、延迟和其他可能阻碍按计划实现项目目标的问题。本研究采用描述性定量方法,这是一种通过分析现有数据来描述项目具体情况的研究方法。本文将讨论Sarana Loka Almika PT. Griya Jenggala开发中的成本差异(CV)和进度差异(SV),评估Griya Jenggala开发中的成本绩效指数(CPI)和进度绩效指数(SPI)以评估其有效性,估算完成Griya Jenggala项目所需的完工成本(EAC)和完工工期(EAS)。并提供对Griya Jenggala开发项目可能产生的潜在利润或损失的估计。
Control Analysis of the Griya Jenggala Development Project using the Earned Value Method at PT Sarana Loka Almika in Kebayoran
Project control is a structured effort to establish standards in accordance with the plan, design information systems, compare implementation with established standards, analyze potential deviations, and take corrective actions necessary to ensure the effective and efficient use of resources in line with the set targets. Each project has its own specific plan and schedule, determining the start and end time of the project, implementation methods, and resource allocation. Operational challenges often arise in project planning, such as resource shortages, improper allocation, delays, and other issues that may hinder the achievement of project goals as planned. This research utilizes a descriptive quantitative approach, which is a research method that describes the specific conditions of the project through the analysis of available data. This article will discuss the cost variance (CV) and schedule variance (SV) in the development of Griya Jenggala at PT. Sarana Loka Almika, evaluate the cost performance index (CPI) and schedule performance index (SPI) in the development of Griya Jenggala to assess its effectiveness, estimate the cost at completion (EAC) and estimated duration at completion (EAS) required to complete the Griya Jenggala project, as well as provide an estimation of potential profits or losses that may arise in the Griya Jenggala development project.