{"title":"尼泊尔Budhinanda市农村公路建设管理面临的挑战评价","authors":"B. R. Joshi","doi":"10.24321/2456.9925.202101","DOIUrl":null,"url":null,"abstract":"The overall objective of the study was to evaluate the management related challenges on upgrading and maintenance of the rural road and to find causes of road construction on an impromptu basis in Budhinandha Municipality.A questionnaire was developed after a literature survey in five-point Likert Scale and surveyed purposively and ranked by Relative Importance Indices (RII). This study revealed that five top-ranked management challenges were found to be dispute on alignment selection, improper water management, release of the budget at end of the fiscal year, land acquisition problem during track opening and widening, lack of clear technical specification and weak geology. And five top-ranked causes of road construction on an ad-hoc basis were budget allocation at end of the fiscal year, political and committee interference during the selection of road alignment, lack of preparation of Transportation Master Plan (TMP), lack of sufficient Technical staff and lack of proper project monitoring by a responsible team of Municipality.The high amount of repair and maintenance cost and environmental protection due to haphazard use of dozer on road construction could significantly be reduced, if government authority enforces to follow design standards, understanding the community value, and implementation of bioengineering approach during road construction.","PeriodicalId":267306,"journal":{"name":"Journal of Advanced Research in Construction and Urban Architecture","volume":"23 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-04-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"An Evaluation of Challenges of Rural Road Construction Management in Budhinanda Municipality, Nepal\",\"authors\":\"B. R. Joshi\",\"doi\":\"10.24321/2456.9925.202101\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The overall objective of the study was to evaluate the management related challenges on upgrading and maintenance of the rural road and to find causes of road construction on an impromptu basis in Budhinandha Municipality.A questionnaire was developed after a literature survey in five-point Likert Scale and surveyed purposively and ranked by Relative Importance Indices (RII). This study revealed that five top-ranked management challenges were found to be dispute on alignment selection, improper water management, release of the budget at end of the fiscal year, land acquisition problem during track opening and widening, lack of clear technical specification and weak geology. And five top-ranked causes of road construction on an ad-hoc basis were budget allocation at end of the fiscal year, political and committee interference during the selection of road alignment, lack of preparation of Transportation Master Plan (TMP), lack of sufficient Technical staff and lack of proper project monitoring by a responsible team of Municipality.The high amount of repair and maintenance cost and environmental protection due to haphazard use of dozer on road construction could significantly be reduced, if government authority enforces to follow design standards, understanding the community value, and implementation of bioengineering approach during road construction.\",\"PeriodicalId\":267306,\"journal\":{\"name\":\"Journal of Advanced Research in Construction and Urban Architecture\",\"volume\":\"23 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-04-12\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Advanced Research in Construction and Urban Architecture\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.24321/2456.9925.202101\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Advanced Research in Construction and Urban Architecture","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24321/2456.9925.202101","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

该研究的总体目标是评估与农村道路升级和维护相关的管理挑战,并找出Budhinandha市临时修建道路的原因。采用李克特五点量表进行文献调查后编制问卷,进行有目的的调查,采用相对重要性指数(Relative Importance Indices, RII)进行排序。研究发现,铁路管理面临的五大挑战分别是:线路选择争议、水资源管理不当、财政年度末预算发放、开通和加宽期间的征地问题、缺乏明确的技术规范和地质薄弱。在临时基础上进行道路建设的五个主要原因是财政年度结束时的预算分配,道路线形选择过程中的政治和委员会干预,缺乏交通总体规划(TMP)的编制,缺乏足够的技术人员以及缺乏市政府负责小组的适当项目监督。如果政府当局在道路建设过程中强制执行设计标准,了解社区价值,并实施生物工程方法,则可以大大减少道路建设中随意使用推土机造成的高额维修和维护成本和环境保护。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
An Evaluation of Challenges of Rural Road Construction Management in Budhinanda Municipality, Nepal
The overall objective of the study was to evaluate the management related challenges on upgrading and maintenance of the rural road and to find causes of road construction on an impromptu basis in Budhinandha Municipality.A questionnaire was developed after a literature survey in five-point Likert Scale and surveyed purposively and ranked by Relative Importance Indices (RII). This study revealed that five top-ranked management challenges were found to be dispute on alignment selection, improper water management, release of the budget at end of the fiscal year, land acquisition problem during track opening and widening, lack of clear technical specification and weak geology. And five top-ranked causes of road construction on an ad-hoc basis were budget allocation at end of the fiscal year, political and committee interference during the selection of road alignment, lack of preparation of Transportation Master Plan (TMP), lack of sufficient Technical staff and lack of proper project monitoring by a responsible team of Municipality.The high amount of repair and maintenance cost and environmental protection due to haphazard use of dozer on road construction could significantly be reduced, if government authority enforces to follow design standards, understanding the community value, and implementation of bioengineering approach during road construction.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信