英格兰和威尔士建筑合同中的延期和违约金

D. Brawn
{"title":"英格兰和威尔士建筑合同中的延期和违约金","authors":"D. Brawn","doi":"10.1108/17561451211211750","DOIUrl":null,"url":null,"abstract":"Purpose – The purpose of this paper is to examine the relationship between extensions of time and payment of liquidated damages under construction contracts in English law.Design/methodology/approach – This paper sets out the law relating to granting extensions of time and liquidated damages and examines the effect of one upon the other. The JCT form of contract is used as an example, although it is submitted that the position is the same under other forms of contract. Case law is examined to illuminate the judicial approach and highlight inconsistencies, and consideration is given to the position in other jurisdictions.Findings – This paper examines the effect of delaying events in particular circumstances, including where time is “at large”, sectional completion, partial possession, set‐off of liquidated damages and liquidated damages after termination of the contract. Particular attention is paid to concurrent and sequential delays; where both parties are at fault, it may be appropriate to deny the emp...","PeriodicalId":158465,"journal":{"name":"International Journal of Law in The Built Environment","volume":"35 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2012-04-13","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"9","resultStr":"{\"title\":\"Extensions of time and liquidated damages in construction contracts in England and Wales\",\"authors\":\"D. Brawn\",\"doi\":\"10.1108/17561451211211750\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Purpose – The purpose of this paper is to examine the relationship between extensions of time and payment of liquidated damages under construction contracts in English law.Design/methodology/approach – This paper sets out the law relating to granting extensions of time and liquidated damages and examines the effect of one upon the other. The JCT form of contract is used as an example, although it is submitted that the position is the same under other forms of contract. Case law is examined to illuminate the judicial approach and highlight inconsistencies, and consideration is given to the position in other jurisdictions.Findings – This paper examines the effect of delaying events in particular circumstances, including where time is “at large”, sectional completion, partial possession, set‐off of liquidated damages and liquidated damages after termination of the contract. Particular attention is paid to concurrent and sequential delays; where both parties are at fault, it may be appropriate to deny the emp...\",\"PeriodicalId\":158465,\"journal\":{\"name\":\"International Journal of Law in The Built Environment\",\"volume\":\"35 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2012-04-13\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"9\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Law in The Built Environment\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1108/17561451211211750\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Law in The Built Environment","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/17561451211211750","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 9

摘要

目的-本文的目的是研究在英国法律下的施工合同延期和支付违约金之间的关系。设计/方法/方法-本文件列出与准予延期和违约金有关的法律,并探讨两者之间的影响。本文以JCT形式的合同为例,但有人指出,在其他形式的合同下情况也是一样的。判例法的审查,以阐明司法途径和突出矛盾,并考虑到其他司法管辖区的立场。研究结果-本文研究了在特定情况下延迟事件的影响,包括时间“不固定”、部分完成、部分占有、抵销违约金和合同终止后的违约金。特别注意并发和顺序延迟;在双方都有过错的情况下,可以适当地否认……
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Extensions of time and liquidated damages in construction contracts in England and Wales
Purpose – The purpose of this paper is to examine the relationship between extensions of time and payment of liquidated damages under construction contracts in English law.Design/methodology/approach – This paper sets out the law relating to granting extensions of time and liquidated damages and examines the effect of one upon the other. The JCT form of contract is used as an example, although it is submitted that the position is the same under other forms of contract. Case law is examined to illuminate the judicial approach and highlight inconsistencies, and consideration is given to the position in other jurisdictions.Findings – This paper examines the effect of delaying events in particular circumstances, including where time is “at large”, sectional completion, partial possession, set‐off of liquidated damages and liquidated damages after termination of the contract. Particular attention is paid to concurrent and sequential delays; where both parties are at fault, it may be appropriate to deny the emp...
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信