超高压输电线路中MOV火花隙保护与FSC的配合

Piyush M. Khadke, N. Patne, G. Shinde
{"title":"超高压输电线路中MOV火花隙保护与FSC的配合","authors":"Piyush M. Khadke, N. Patne, G. Shinde","doi":"10.1109/WIECON-ECE.2016.8009077","DOIUrl":null,"url":null,"abstract":"This paper highlights a real time practical case study of 40% Fixed Series Compensation (FSC) installed at 1200/765/400/220 kV Wardha Substation, Power Grid Corporation of India Ltd., WR - I (Western Region - I), India under Western Region Strengthening Scheme (WRSS). The novel finding in this research work is the operation of Spark gap in co-ordination with Metal Oxide Varistor (MOV) during various internal fault conditions, according to the threshold energy which contradicts the assumptions made in some of the previous research works. For increasing the power capacity and meeting the rising power demands, it is implemented on 400 kV double circuit Raipur - Wardha Line (375 km). This paper focuses on the effects of FSC on the specified line studied by comparing simulated results with real time data. It also dwells into fault analysis aspects of the specified line with FSC.","PeriodicalId":412645,"journal":{"name":"2016 IEEE International WIE Conference on Electrical and Computer Engineering (WIECON-ECE)","volume":"5 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2016-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Co-ordination of spark gap protection with MOV in EHV transmission line with FSC\",\"authors\":\"Piyush M. Khadke, N. Patne, G. Shinde\",\"doi\":\"10.1109/WIECON-ECE.2016.8009077\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper highlights a real time practical case study of 40% Fixed Series Compensation (FSC) installed at 1200/765/400/220 kV Wardha Substation, Power Grid Corporation of India Ltd., WR - I (Western Region - I), India under Western Region Strengthening Scheme (WRSS). The novel finding in this research work is the operation of Spark gap in co-ordination with Metal Oxide Varistor (MOV) during various internal fault conditions, according to the threshold energy which contradicts the assumptions made in some of the previous research works. For increasing the power capacity and meeting the rising power demands, it is implemented on 400 kV double circuit Raipur - Wardha Line (375 km). This paper focuses on the effects of FSC on the specified line studied by comparing simulated results with real time data. It also dwells into fault analysis aspects of the specified line with FSC.\",\"PeriodicalId\":412645,\"journal\":{\"name\":\"2016 IEEE International WIE Conference on Electrical and Computer Engineering (WIECON-ECE)\",\"volume\":\"5 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2016-12-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2016 IEEE International WIE Conference on Electrical and Computer Engineering (WIECON-ECE)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/WIECON-ECE.2016.8009077\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2016 IEEE International WIE Conference on Electrical and Computer Engineering (WIECON-ECE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/WIECON-ECE.2016.8009077","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

本文重点介绍了在印度西部地区加强计划(WRSS)下,印度电网公司WR - I(西部地区- I) 1200/765/400/220千伏瓦尔达变电站安装40%固定串联补偿(FSC)的实时实际案例研究。本研究的新发现是在各种内部故障条件下,火花间隙与金属氧化物压敏电阻(MOV)根据阈值能量协同工作,这与以往一些研究工作的假设相矛盾。为了增加电力容量,满足日益增长的电力需求,在400千伏双回路赖布尔-瓦尔达线(375公里)上实施。本文通过仿真结果与实时数据的对比,重点研究了FSC对指定线路的影响。本文还详细介绍了用FSC对指定线路进行故障分析的方法。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Co-ordination of spark gap protection with MOV in EHV transmission line with FSC
This paper highlights a real time practical case study of 40% Fixed Series Compensation (FSC) installed at 1200/765/400/220 kV Wardha Substation, Power Grid Corporation of India Ltd., WR - I (Western Region - I), India under Western Region Strengthening Scheme (WRSS). The novel finding in this research work is the operation of Spark gap in co-ordination with Metal Oxide Varistor (MOV) during various internal fault conditions, according to the threshold energy which contradicts the assumptions made in some of the previous research works. For increasing the power capacity and meeting the rising power demands, it is implemented on 400 kV double circuit Raipur - Wardha Line (375 km). This paper focuses on the effects of FSC on the specified line studied by comparing simulated results with real time data. It also dwells into fault analysis aspects of the specified line with FSC.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信