{"title":"马来西亚建筑保护投标中差异大的原因","authors":"Lim Yoke Mui, Y. Ahmad, F. Nabavi","doi":"10.1108/SS-04-2015-0023","DOIUrl":null,"url":null,"abstract":"Purpose – The purpose of this paper is to identify the reasons for the variance among tenders for conservation projects in Malaysia. Design/methodology/approach – Semi-structured interview approach was adopted because this method allows for effective probing of issues. The interviews are conducted with experienced conservation contractors. The interviews are transcribed and the data are analysed using thematic analysis. Coefficient of variation (CV) measure was also used to determine the level of variance that occurs in tenders for conservation projects. Findings – The study found that contractors faced difficulty in pricing competitively due to the following four factors, namely, uncertain information on the actual work on site, inexperience in conservation construction works, information in the bill of quantities is incomplete and uncertain labour and material cost. The study of 22 tenders also ascertains that there is a high variance among the tenderers for building conservation projects. This is deter...","PeriodicalId":118605,"journal":{"name":"Structural Survey","volume":"31 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2016-04-25","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"5","resultStr":"{\"title\":\"Causes of high variance in building conservation tenders in Malaysia\",\"authors\":\"Lim Yoke Mui, Y. Ahmad, F. Nabavi\",\"doi\":\"10.1108/SS-04-2015-0023\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Purpose – The purpose of this paper is to identify the reasons for the variance among tenders for conservation projects in Malaysia. Design/methodology/approach – Semi-structured interview approach was adopted because this method allows for effective probing of issues. The interviews are conducted with experienced conservation contractors. The interviews are transcribed and the data are analysed using thematic analysis. Coefficient of variation (CV) measure was also used to determine the level of variance that occurs in tenders for conservation projects. Findings – The study found that contractors faced difficulty in pricing competitively due to the following four factors, namely, uncertain information on the actual work on site, inexperience in conservation construction works, information in the bill of quantities is incomplete and uncertain labour and material cost. The study of 22 tenders also ascertains that there is a high variance among the tenderers for building conservation projects. This is deter...\",\"PeriodicalId\":118605,\"journal\":{\"name\":\"Structural Survey\",\"volume\":\"31 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2016-04-25\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"5\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Structural Survey\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1108/SS-04-2015-0023\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Structural Survey","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/SS-04-2015-0023","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 5

摘要

目的-本文的目的是确定马来西亚保护项目招标差异的原因。设计/方法/方法-采用半结构化访谈方法,因为这种方法可以有效地探究问题。访谈是由经验丰富的保育承建商进行的。采访记录和数据分析使用专题分析。变异系数(CV)测量也被用于确定在保护项目投标中发生的变异水平。调查结果-研究发现,承建商在定价时遇到困难,主要是由于以下四个因素,即有关现场实际工程的资料不确定、在保育建筑工程方面缺乏经验、工程量清单资料不完整,以及劳力及物料成本不确定。对22份投标书的研究也确定了建筑保育项目的投标者之间存在很大差异。这是威慑……
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Causes of high variance in building conservation tenders in Malaysia
Purpose – The purpose of this paper is to identify the reasons for the variance among tenders for conservation projects in Malaysia. Design/methodology/approach – Semi-structured interview approach was adopted because this method allows for effective probing of issues. The interviews are conducted with experienced conservation contractors. The interviews are transcribed and the data are analysed using thematic analysis. Coefficient of variation (CV) measure was also used to determine the level of variance that occurs in tenders for conservation projects. Findings – The study found that contractors faced difficulty in pricing competitively due to the following four factors, namely, uncertain information on the actual work on site, inexperience in conservation construction works, information in the bill of quantities is incomplete and uncertain labour and material cost. The study of 22 tenders also ascertains that there is a high variance among the tenderers for building conservation projects. This is deter...
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信