{"title":"分析侧线绩效评估分析。18号公路。jaya Jiwo使用PKJI 2014","authors":"Eko Prayitno, Z. Abidin, M. Huda","doi":"10.25139/JPRS.V2I1.1491","DOIUrl":null,"url":null,"abstract":"Jl. Raya Nginden - Jl. Raya Panjang Jiwo intersection is an intersection that has a high density level, especially at peak hour, it can be seen from the length of the queue. The aim of this study is to determine the intersection performance in existing conditions and the next 5 (five) years and give a recommendation for improving an intersection performance. For analyzing intersection traffic performance using Indonesian Road Capacity Guidelines method (PKJI 2014). Primary data in this study are traffic volume, intersection geometric conditions, and cycle times. While secondary data in this study are population data, vehicle growth data, and traffic data from CCTV. Data retrieval in one day of weekday and one day of weekend. The results show that the degree of saturation (DJ) of existing (in 2018) on Wednesday, North approach is 1.45, South 1.35, West 0.76, East 1.49 and existing DJ on Sunday approaching North 0.80, South 0.88, West 0.69 and East 1.12. For traffic performance in the next five years (in 2023) with existing cycle and phase times, DJ on Wednesday, North approach is 2.36, South 2.20, West 1.24, East 2.43 and DJ values on Sunday, North approach is 1.30, South 1.42, West 0.95 and East 1.81. For traffic performance improving at the intersection is made an alternative with changing the cycle time and movement phase which show the results in existing DJ (2018) on Wednesday for North approach is 0.86, South 0.92, West 0.77, East 0.43 and DJ on Sunday for North approach is 0.52 , South 0.67, West 0.52 and East 0.28. For the next five years' traffic performance (in 2023), DJ on Wednesday for North approach is 1.45, South 1.67, West 1.35, East 0.91 and existing DJ on Sunday for North approach is 0.88, South 1.22, West 0.92 and East 0.60.","PeriodicalId":111362,"journal":{"name":"Ge-STRAM: Jurnal Perencanaan dan Rekayasa Sipil","volume":"86 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-03-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Analisis Evaluasi Kinerja Simpang Bersinyal Jl. Raya Nginden - Jl. Raya Panjang Jiwo Menggunakan PKJI 2014\",\"authors\":\"Eko Prayitno, Z. Abidin, M. Huda\",\"doi\":\"10.25139/JPRS.V2I1.1491\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Jl. Raya Nginden - Jl. Raya Panjang Jiwo intersection is an intersection that has a high density level, especially at peak hour, it can be seen from the length of the queue. The aim of this study is to determine the intersection performance in existing conditions and the next 5 (five) years and give a recommendation for improving an intersection performance. For analyzing intersection traffic performance using Indonesian Road Capacity Guidelines method (PKJI 2014). Primary data in this study are traffic volume, intersection geometric conditions, and cycle times. While secondary data in this study are population data, vehicle growth data, and traffic data from CCTV. Data retrieval in one day of weekday and one day of weekend. The results show that the degree of saturation (DJ) of existing (in 2018) on Wednesday, North approach is 1.45, South 1.35, West 0.76, East 1.49 and existing DJ on Sunday approaching North 0.80, South 0.88, West 0.69 and East 1.12. For traffic performance in the next five years (in 2023) with existing cycle and phase times, DJ on Wednesday, North approach is 2.36, South 2.20, West 1.24, East 2.43 and DJ values on Sunday, North approach is 1.30, South 1.42, West 0.95 and East 1.81. For traffic performance improving at the intersection is made an alternative with changing the cycle time and movement phase which show the results in existing DJ (2018) on Wednesday for North approach is 0.86, South 0.92, West 0.77, East 0.43 and DJ on Sunday for North approach is 0.52 , South 0.67, West 0.52 and East 0.28. For the next five years' traffic performance (in 2023), DJ on Wednesday for North approach is 1.45, South 1.67, West 1.35, East 0.91 and existing DJ on Sunday for North approach is 0.88, South 1.22, West 0.92 and East 0.60.\",\"PeriodicalId\":111362,\"journal\":{\"name\":\"Ge-STRAM: Jurnal Perencanaan dan Rekayasa Sipil\",\"volume\":\"86 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-03-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Ge-STRAM: Jurnal Perencanaan dan Rekayasa Sipil\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.25139/JPRS.V2I1.1491\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Ge-STRAM: Jurnal Perencanaan dan Rekayasa Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.25139/JPRS.V2I1.1491","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2
摘要
杰。Raya Nginden - jr。Raya Panjang Jiwo路口是一个高密度水平的路口,特别是在高峰时段,从排队的长度可以看出。本研究的目的是确定交叉口在现有条件下和未来5年的性能,并给出改善交叉口性能的建议。使用印度尼西亚道路容量指南方法(PKJI 2014)分析交叉口交通性能。本研究的主要数据是交通量、交叉口几何条件和周期时间。而本研究的辅助数据是来自CCTV的人口数据、车辆增长数据和交通数据。数据检索,工作日一天,周末一天。结果表明:现有(2018年)周三、北接近1.45、南接近1.35、西接近0.76、东接近1.49;周日现有DJ接近北0.80、南接近0.88、西接近0.69、东接近1.12。对于未来5年(2023年)在现有周期和相位下的交通表现,周三的DJ,北进为2.36,南进为2.20,西进为1.24,东进为2.43,周日的DJ值,北进为1.30,南进为1.42,西进0.95,东进1.81。为了改善十字路口的交通性能,通过改变周期时间和运动相位,显示现有DJ(2018)周三北进的结果为0.86,南0.92,西0.77,东0.43,周日DJ北进的结果为0.52,南0.67,西0.52和东0.28。对于未来五年的交通表现(2023年),周三北进路的DJ为1.45,南进路1.67,西进路1.35,东进路0.91,现有周日北进路的DJ为0.88,南进路1.22,西进路0.92,东进路0.60。
Analisis Evaluasi Kinerja Simpang Bersinyal Jl. Raya Nginden - Jl. Raya Panjang Jiwo Menggunakan PKJI 2014
Jl. Raya Nginden - Jl. Raya Panjang Jiwo intersection is an intersection that has a high density level, especially at peak hour, it can be seen from the length of the queue. The aim of this study is to determine the intersection performance in existing conditions and the next 5 (five) years and give a recommendation for improving an intersection performance. For analyzing intersection traffic performance using Indonesian Road Capacity Guidelines method (PKJI 2014). Primary data in this study are traffic volume, intersection geometric conditions, and cycle times. While secondary data in this study are population data, vehicle growth data, and traffic data from CCTV. Data retrieval in one day of weekday and one day of weekend. The results show that the degree of saturation (DJ) of existing (in 2018) on Wednesday, North approach is 1.45, South 1.35, West 0.76, East 1.49 and existing DJ on Sunday approaching North 0.80, South 0.88, West 0.69 and East 1.12. For traffic performance in the next five years (in 2023) with existing cycle and phase times, DJ on Wednesday, North approach is 2.36, South 2.20, West 1.24, East 2.43 and DJ values on Sunday, North approach is 1.30, South 1.42, West 0.95 and East 1.81. For traffic performance improving at the intersection is made an alternative with changing the cycle time and movement phase which show the results in existing DJ (2018) on Wednesday for North approach is 0.86, South 0.92, West 0.77, East 0.43 and DJ on Sunday for North approach is 0.52 , South 0.67, West 0.52 and East 0.28. For the next five years' traffic performance (in 2023), DJ on Wednesday for North approach is 1.45, South 1.67, West 1.35, East 0.91 and existing DJ on Sunday for North approach is 0.88, South 1.22, West 0.92 and East 0.60.