{"title":"基于土体统一运动模型的盾构变形预测及加固方案优化选择","authors":"Xu Xinxing, Zhang Jichao, Chen Hang","doi":"10.21276/ijee.2017.10.0229","DOIUrl":null,"url":null,"abstract":": In order to control the construction deformation of the tunnel under the existing highway, the pavement deformation under the condition of the tunnel section of shield tunnel in Shanghai was calculated. The deformation of the pavement under the condition of the tunnel was calculated, and numerical simulation is carried out with FLAC3D numerical simulation. In view of the original pavement deformation amount and shield construction deformation increment and over the pavement deformation specification maximum allowable value of contrast the single grouting reinforcement, setting pile and grouting combined with the road pile foundation reinforcement of three different reinforcement scheme is determined. Through the numerical simulation analysis to determine the scheme for the optimal solution, after the construction of the comparison of the actual deformation, second scheme on deformation control is better than expected. It is proved that the prediction with high accuracy and this is an important reference for similar projects.","PeriodicalId":344962,"journal":{"name":"International journal of Earth Sciences and Engineering","volume":"113 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2017-04-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Deformation Prediction of Shield Construction Based Soil Unified Movement Model and Optimization Selection of the Reinforcement Schemes\",\"authors\":\"Xu Xinxing, Zhang Jichao, Chen Hang\",\"doi\":\"10.21276/ijee.2017.10.0229\",\"DOIUrl\":null,\"url\":null,\"abstract\":\": In order to control the construction deformation of the tunnel under the existing highway, the pavement deformation under the condition of the tunnel section of shield tunnel in Shanghai was calculated. The deformation of the pavement under the condition of the tunnel was calculated, and numerical simulation is carried out with FLAC3D numerical simulation. In view of the original pavement deformation amount and shield construction deformation increment and over the pavement deformation specification maximum allowable value of contrast the single grouting reinforcement, setting pile and grouting combined with the road pile foundation reinforcement of three different reinforcement scheme is determined. Through the numerical simulation analysis to determine the scheme for the optimal solution, after the construction of the comparison of the actual deformation, second scheme on deformation control is better than expected. It is proved that the prediction with high accuracy and this is an important reference for similar projects.\",\"PeriodicalId\":344962,\"journal\":{\"name\":\"International journal of Earth Sciences and Engineering\",\"volume\":\"113 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2017-04-26\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International journal of Earth Sciences and Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.21276/ijee.2017.10.0229\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International journal of Earth Sciences and Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21276/ijee.2017.10.0229","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

为控制隧道在既有公路作用下的施工变形,对上海某盾构隧道隧道段条件下的路面变形进行了计算。对隧道条件下路面变形进行了计算,并利用FLAC3D数值模拟软件进行了数值模拟。针对原有路面变形量与盾构施工变形增量及超过路面变形规范最大容许值的对比,确定了设置桩和注浆结合道路桩基加固的三种不同加固方案。通过数值模拟分析确定方案为最优解,经过与施工实际变形情况的对比,第二方案对变形的控制效果优于预期。实践证明,该方法具有较高的预测精度,对类似工程具有重要的参考价值。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Deformation Prediction of Shield Construction Based Soil Unified Movement Model and Optimization Selection of the Reinforcement Schemes
: In order to control the construction deformation of the tunnel under the existing highway, the pavement deformation under the condition of the tunnel section of shield tunnel in Shanghai was calculated. The deformation of the pavement under the condition of the tunnel was calculated, and numerical simulation is carried out with FLAC3D numerical simulation. In view of the original pavement deformation amount and shield construction deformation increment and over the pavement deformation specification maximum allowable value of contrast the single grouting reinforcement, setting pile and grouting combined with the road pile foundation reinforcement of three different reinforcement scheme is determined. Through the numerical simulation analysis to determine the scheme for the optimal solution, after the construction of the comparison of the actual deformation, second scheme on deformation control is better than expected. It is proved that the prediction with high accuracy and this is an important reference for similar projects.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信