{"title":"高层工程结构应急措施的施工技术方案优化","authors":"O. Menejljuk","doi":"10.36059/978-966-397-165-0/45-68","DOIUrl":null,"url":null,"abstract":"INTRODUCTION There is a large number of high-rise engineering structures in Ukraine and abroad. Most of them are operated by ten years or more. Many high-rise engineering facilities require repair work, and some – emergently. Such projects require a significant investment. As a rule, there are many options for the upgrade. They may have different costs, deadlines. The specificity of some objects requires a specific schedule (only on the night shift, the use of a limited number of people or calendar time). The regulations and information sources have no guidance on the selection of effective organizational and technological decisions at reconstruction of such buildings. The use of traditional building processes modeling methods makes it impossible to evaluate the effectiveness of variants of organizational and technological solutions. Modeling of these options and experimental analysis of statistical models will determine the best solution for the selected performance criteria.","PeriodicalId":305447,"journal":{"name":"ORGANIZATIONAL AND TECHNOLOGICAL MODEL ENGINEERING IN THE CONSTRUCTION INDUSTRY","volume":"418 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"OPTIMIZATION OF CONSTRUCTIVE AND TECHNOLOGICAL SOLUTIONS OF HIGH-RISE ENGINEERING STRUCTURES EMERGENCY MEASURES\",\"authors\":\"O. Menejljuk\",\"doi\":\"10.36059/978-966-397-165-0/45-68\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"INTRODUCTION There is a large number of high-rise engineering structures in Ukraine and abroad. Most of them are operated by ten years or more. Many high-rise engineering facilities require repair work, and some – emergently. Such projects require a significant investment. As a rule, there are many options for the upgrade. They may have different costs, deadlines. The specificity of some objects requires a specific schedule (only on the night shift, the use of a limited number of people or calendar time). The regulations and information sources have no guidance on the selection of effective organizational and technological decisions at reconstruction of such buildings. The use of traditional building processes modeling methods makes it impossible to evaluate the effectiveness of variants of organizational and technological solutions. Modeling of these options and experimental analysis of statistical models will determine the best solution for the selected performance criteria.\",\"PeriodicalId\":305447,\"journal\":{\"name\":\"ORGANIZATIONAL AND TECHNOLOGICAL MODEL ENGINEERING IN THE CONSTRUCTION INDUSTRY\",\"volume\":\"418 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"ORGANIZATIONAL AND TECHNOLOGICAL MODEL ENGINEERING IN THE CONSTRUCTION INDUSTRY\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.36059/978-966-397-165-0/45-68\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"ORGANIZATIONAL AND TECHNOLOGICAL MODEL ENGINEERING IN THE CONSTRUCTION INDUSTRY","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.36059/978-966-397-165-0/45-68","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

在乌克兰和国外有大量的高层工程结构。其中大多数是十年或更长时间的运营。许多高层工程设施需要维修,有些是紧急维修。这样的项目需要大量的投资。一般来说,升级有很多选择。它们可能有不同的成本和期限。某些对象的特殊性要求有特定的日程安排(仅限夜班、使用有限的人或日历时间)。条例和信息来源没有指导在重建这些建筑物时选择有效的组织和技术决策。传统建筑过程建模方法的使用使得不可能评估组织和技术解决方案变体的有效性。这些选项的建模和统计模型的实验分析将确定所选性能标准的最佳解决方案。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
OPTIMIZATION OF CONSTRUCTIVE AND TECHNOLOGICAL SOLUTIONS OF HIGH-RISE ENGINEERING STRUCTURES EMERGENCY MEASURES
INTRODUCTION There is a large number of high-rise engineering structures in Ukraine and abroad. Most of them are operated by ten years or more. Many high-rise engineering facilities require repair work, and some – emergently. Such projects require a significant investment. As a rule, there are many options for the upgrade. They may have different costs, deadlines. The specificity of some objects requires a specific schedule (only on the night shift, the use of a limited number of people or calendar time). The regulations and information sources have no guidance on the selection of effective organizational and technological decisions at reconstruction of such buildings. The use of traditional building processes modeling methods makes it impossible to evaluate the effectiveness of variants of organizational and technological solutions. Modeling of these options and experimental analysis of statistical models will determine the best solution for the selected performance criteria.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信