{"title":"使用存储库挖掘的软件开发项目的轻量级风险缓解","authors":"S. P. Masticola","doi":"10.1109/MSR.2007.16","DOIUrl":null,"url":null,"abstract":"Many software projects fail to deliver their needed results on-time and on-budget. There are a variety of reasons why this may occur. For some of these reasons (notably deterioration of the codebase), corrective action is often difficult to cost-justify or to implement efficiently in practice. To address this, an approach of lightweight risk mitigation is proposed: mine risk data from configuration management and defect tracking systems, integrate this data with project-cost data in a flexible dashboard, and facilitate strategic refactoring with semi-custom transforms where necessary. This prescriptive information would simultaneously help the project manager to cost-justify repair efforts and lowers the cost of finding and fixing hot spots.","PeriodicalId":201749,"journal":{"name":"Fourth International Workshop on Mining Software Repositories (MSR'07:ICSE Workshops 2007)","volume":"41 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2007-05-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"Lightweight Risk Mitigation for Software Development Projects Using Repository Mining\",\"authors\":\"S. P. Masticola\",\"doi\":\"10.1109/MSR.2007.16\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Many software projects fail to deliver their needed results on-time and on-budget. There are a variety of reasons why this may occur. For some of these reasons (notably deterioration of the codebase), corrective action is often difficult to cost-justify or to implement efficiently in practice. To address this, an approach of lightweight risk mitigation is proposed: mine risk data from configuration management and defect tracking systems, integrate this data with project-cost data in a flexible dashboard, and facilitate strategic refactoring with semi-custom transforms where necessary. This prescriptive information would simultaneously help the project manager to cost-justify repair efforts and lowers the cost of finding and fixing hot spots.\",\"PeriodicalId\":201749,\"journal\":{\"name\":\"Fourth International Workshop on Mining Software Repositories (MSR'07:ICSE Workshops 2007)\",\"volume\":\"41 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2007-05-20\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Fourth International Workshop on Mining Software Repositories (MSR'07:ICSE Workshops 2007)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/MSR.2007.16\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Fourth International Workshop on Mining Software Repositories (MSR'07:ICSE Workshops 2007)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/MSR.2007.16","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Lightweight Risk Mitigation for Software Development Projects Using Repository Mining
Many software projects fail to deliver their needed results on-time and on-budget. There are a variety of reasons why this may occur. For some of these reasons (notably deterioration of the codebase), corrective action is often difficult to cost-justify or to implement efficiently in practice. To address this, an approach of lightweight risk mitigation is proposed: mine risk data from configuration management and defect tracking systems, integrate this data with project-cost data in a flexible dashboard, and facilitate strategic refactoring with semi-custom transforms where necessary. This prescriptive information would simultaneously help the project manager to cost-justify repair efforts and lowers the cost of finding and fixing hot spots.