基于LSM的铁路建设工期计算模型研究

Liqiang Liu, Yisheng Liu, Yuanjie Tang
{"title":"基于LSM的铁路建设工期计算模型研究","authors":"Liqiang Liu, Yisheng Liu, Yuanjie Tang","doi":"10.1109/LISS.2015.7369805","DOIUrl":null,"url":null,"abstract":"Reasonable duration is very important in terms of construction. This study presents a new model for calculate the railway construction project duration by means of linear Scheduling method. It gives two kinds of activity combination, the two respectively the calculation method of combination of the construction duration. And the duration of the validity of the proposed method are determined verified by an actual railway project instance.","PeriodicalId":124091,"journal":{"name":"2015 International Conference on Logistics, Informatics and Service Sciences (LISS)","volume":"40 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2015-07-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Study on duration calculate model of railway construction based on LSM\",\"authors\":\"Liqiang Liu, Yisheng Liu, Yuanjie Tang\",\"doi\":\"10.1109/LISS.2015.7369805\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Reasonable duration is very important in terms of construction. This study presents a new model for calculate the railway construction project duration by means of linear Scheduling method. It gives two kinds of activity combination, the two respectively the calculation method of combination of the construction duration. And the duration of the validity of the proposed method are determined verified by an actual railway project instance.\",\"PeriodicalId\":124091,\"journal\":{\"name\":\"2015 International Conference on Logistics, Informatics and Service Sciences (LISS)\",\"volume\":\"40 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2015-07-27\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2015 International Conference on Logistics, Informatics and Service Sciences (LISS)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/LISS.2015.7369805\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2015 International Conference on Logistics, Informatics and Service Sciences (LISS)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/LISS.2015.7369805","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

合理的工期在施工中是非常重要的。本文提出了用线性调度法计算铁路建设项目工期的新模型。给出了两种工程组合,分别给出了两种工程组合工期的计算方法。并通过实际工程实例验证了该方法的有效性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Study on duration calculate model of railway construction based on LSM
Reasonable duration is very important in terms of construction. This study presents a new model for calculate the railway construction project duration by means of linear Scheduling method. It gives two kinds of activity combination, the two respectively the calculation method of combination of the construction duration. And the duration of the validity of the proposed method are determined verified by an actual railway project instance.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信