风险管理与关键链计划相结合的可靠项目计划

S. Mansoorzadeh, S. Mohd Yusof
{"title":"风险管理与关键链计划相结合的可靠项目计划","authors":"S. Mansoorzadeh, S. Mohd Yusof","doi":"10.1109/SCORED.2011.6148780","DOIUrl":null,"url":null,"abstract":"This paper proposes a reliable project scheduling approach, considering the integration of both risk management and critical chain schedule analysis. Various risks and uncertainties exist in projects. These may not only prevent the projects to be completed within budget and time limit, but also threaten the quality, safety and operational needs. In the proposed method the potential project risks are analyzed and risk response strategies are developed by fuzzy failure mode and effect analysis (FMEA) and then varying effect of each risk over each activity. The project total time can then be quantified and simulated by Monte Carlo simulation that is effective in uncertain conditions due to its capability of converting uncertainty to risk judgmentally in projects. Following this procedure Fault tree analysis and event tree analysis will be used to get risk mitigation. Eventually, for a reliable schedule we distribute a critical chain schedule which able to implement the project as planned and obtain reasonable Feeding Buffer time and Project Buffer time.","PeriodicalId":383828,"journal":{"name":"2011 IEEE Student Conference on Research and Development","volume":"3 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2011-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"8","resultStr":"{\"title\":\"Reliable project scheduling with combination of risk management and critical chain schedule\",\"authors\":\"S. Mansoorzadeh, S. Mohd Yusof\",\"doi\":\"10.1109/SCORED.2011.6148780\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper proposes a reliable project scheduling approach, considering the integration of both risk management and critical chain schedule analysis. Various risks and uncertainties exist in projects. These may not only prevent the projects to be completed within budget and time limit, but also threaten the quality, safety and operational needs. In the proposed method the potential project risks are analyzed and risk response strategies are developed by fuzzy failure mode and effect analysis (FMEA) and then varying effect of each risk over each activity. The project total time can then be quantified and simulated by Monte Carlo simulation that is effective in uncertain conditions due to its capability of converting uncertainty to risk judgmentally in projects. Following this procedure Fault tree analysis and event tree analysis will be used to get risk mitigation. Eventually, for a reliable schedule we distribute a critical chain schedule which able to implement the project as planned and obtain reasonable Feeding Buffer time and Project Buffer time.\",\"PeriodicalId\":383828,\"journal\":{\"name\":\"2011 IEEE Student Conference on Research and Development\",\"volume\":\"3 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2011-12-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"8\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2011 IEEE Student Conference on Research and Development\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/SCORED.2011.6148780\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2011 IEEE Student Conference on Research and Development","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/SCORED.2011.6148780","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 8

摘要

本文提出了一种综合考虑风险管理和关键链调度分析的可靠项目调度方法。项目中存在各种风险和不确定性。这不仅会阻碍项目在预算和时间内完成,而且会威胁到质量、安全和运营需求。该方法通过模糊失效模式和影响分析(FMEA)对项目的潜在风险进行分析,并制定风险响应策略,然后对每个风险对每个活动的影响进行变化分析。然后,项目总时间可以通过蒙特卡罗模拟进行量化和模拟,该模拟在不确定条件下是有效的,因为它能够将项目中的不确定性转换为风险判断。按照此过程,将使用故障树分析和事件树分析来降低风险。最终,对于一个可靠的时间表,我们分配了一个关键链时间表,该时间表能够按计划实施项目,并获得合理的喂入缓冲时间和项目缓冲时间。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Reliable project scheduling with combination of risk management and critical chain schedule
This paper proposes a reliable project scheduling approach, considering the integration of both risk management and critical chain schedule analysis. Various risks and uncertainties exist in projects. These may not only prevent the projects to be completed within budget and time limit, but also threaten the quality, safety and operational needs. In the proposed method the potential project risks are analyzed and risk response strategies are developed by fuzzy failure mode and effect analysis (FMEA) and then varying effect of each risk over each activity. The project total time can then be quantified and simulated by Monte Carlo simulation that is effective in uncertain conditions due to its capability of converting uncertainty to risk judgmentally in projects. Following this procedure Fault tree analysis and event tree analysis will be used to get risk mitigation. Eventually, for a reliable schedule we distribute a critical chain schedule which able to implement the project as planned and obtain reasonable Feeding Buffer time and Project Buffer time.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信