{"title":"仪器仪表和监控","authors":"Xxyyzz, Standard Design","doi":"10.1002/9781119489047.ch24","DOIUrl":null,"url":null,"abstract":"A detailed plan for monitoring possible ground surface movements caused by the microtunneling operations should be prepared. The plan is typically prepared by the engineer in consultation with potentially affected facility owners, as described in Section 13.5. The plan should address the equipment, method, and frequency of survey measurements. The engineer should identify special monitoring requirements. A baseline survey needs to be conducted before the start of construction sufficiently early to establish preexisting conditions. In addition to baseline surveys, before construction the contractor should document existing conditions of potentially affected structures, utilities, and facilities. The documentation of existing conditions establishes a baseline against which damage claims can be evaluated. Before the installation of instrumentation, the contractor should meet with the engineer to discuss frequency and formatting of reports as well as action levels and contingency plans.","PeriodicalId":258678,"journal":{"name":"Aquaculture Engineering","volume":"8 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-10-25","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Instrumentation and Monitoring\",\"authors\":\"Xxyyzz, Standard Design\",\"doi\":\"10.1002/9781119489047.ch24\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"A detailed plan for monitoring possible ground surface movements caused by the microtunneling operations should be prepared. The plan is typically prepared by the engineer in consultation with potentially affected facility owners, as described in Section 13.5. The plan should address the equipment, method, and frequency of survey measurements. The engineer should identify special monitoring requirements. A baseline survey needs to be conducted before the start of construction sufficiently early to establish preexisting conditions. In addition to baseline surveys, before construction the contractor should document existing conditions of potentially affected structures, utilities, and facilities. The documentation of existing conditions establishes a baseline against which damage claims can be evaluated. Before the installation of instrumentation, the contractor should meet with the engineer to discuss frequency and formatting of reports as well as action levels and contingency plans.\",\"PeriodicalId\":258678,\"journal\":{\"name\":\"Aquaculture Engineering\",\"volume\":\"8 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-10-25\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Aquaculture Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1002/9781119489047.ch24\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Aquaculture Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1002/9781119489047.ch24","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

应制订详细计划,监测微隧道作业可能造成的地表移动。如第13.5节所述,该计划通常由工程师与可能受影响的设施所有者协商后编制。该计划应说明调查测量的设备、方法和频率。工程师应确定特殊的监测要求。在施工开始之前,需要进行基线调查,以便尽早确定先前存在的条件。除了基线调查外,在施工之前,承包商应记录潜在受影响的结构、公用设施和设施的现有状况。现有情况的文件建立了一个基线,可据此评估损害索赔。在安装仪器之前,承包商应与工程师会面,讨论报告的频率和格式以及行动水平和应急计划。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Instrumentation and Monitoring
A detailed plan for monitoring possible ground surface movements caused by the microtunneling operations should be prepared. The plan is typically prepared by the engineer in consultation with potentially affected facility owners, as described in Section 13.5. The plan should address the equipment, method, and frequency of survey measurements. The engineer should identify special monitoring requirements. A baseline survey needs to be conducted before the start of construction sufficiently early to establish preexisting conditions. In addition to baseline surveys, before construction the contractor should document existing conditions of potentially affected structures, utilities, and facilities. The documentation of existing conditions establishes a baseline against which damage claims can be evaluated. Before the installation of instrumentation, the contractor should meet with the engineer to discuss frequency and formatting of reports as well as action levels and contingency plans.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信