某工程公司合作项目管理系统开发经验

N. Vurdova
{"title":"某工程公司合作项目管理系统开发经验","authors":"N. Vurdova","doi":"10.12737/2587-6279-2021-9-4-21-29","DOIUrl":null,"url":null,"abstract":"The article deals with the problems of developing a corporate project management system in an engineering company that implements \"full-cycle\" projects - from object design to commissioning in the field of industrial water treatment and water treatment. The problems are connected, first of all, with the achieved level of maturity of the business, the fear of any changes, when the stability of the result is more important than further development. The analysis of the process of working on the project from the stage of initiation to completion was carried out, the most problematic, bottlenecks in the current project management system were identified. Based on the conducted research, the company's management has developed and approved a plan for the development of CSU for the next year and for the future.","PeriodicalId":357307,"journal":{"name":"Scientific Research and Development. Russian Journal of Project Management","volume":"10 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-07-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Development experience of Cooperative Project Management System in an Engineering Company\",\"authors\":\"N. Vurdova\",\"doi\":\"10.12737/2587-6279-2021-9-4-21-29\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The article deals with the problems of developing a corporate project management system in an engineering company that implements \\\"full-cycle\\\" projects - from object design to commissioning in the field of industrial water treatment and water treatment. The problems are connected, first of all, with the achieved level of maturity of the business, the fear of any changes, when the stability of the result is more important than further development. The analysis of the process of working on the project from the stage of initiation to completion was carried out, the most problematic, bottlenecks in the current project management system were identified. Based on the conducted research, the company's management has developed and approved a plan for the development of CSU for the next year and for the future.\",\"PeriodicalId\":357307,\"journal\":{\"name\":\"Scientific Research and Development. Russian Journal of Project Management\",\"volume\":\"10 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-07-08\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Scientific Research and Development. Russian Journal of Project Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.12737/2587-6279-2021-9-4-21-29\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Scientific Research and Development. Russian Journal of Project Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.12737/2587-6279-2021-9-4-21-29","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

本文论述了某工程公司在工业水处理和水处理领域实施“全周期”项目从对象设计到调试的企业项目管理系统的开发问题。首先,当结果的稳定性比进一步发展更重要时,这些问题与业务的成熟程度、对任何变化的恐惧有关。对项目从启动到完成的工作过程进行了分析,确定了当前项目管理系统中存在的最大问题和瓶颈。根据所进行的研究,公司管理层制定并批准了CSU明年和未来的发展计划。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Development experience of Cooperative Project Management System in an Engineering Company
The article deals with the problems of developing a corporate project management system in an engineering company that implements "full-cycle" projects - from object design to commissioning in the field of industrial water treatment and water treatment. The problems are connected, first of all, with the achieved level of maturity of the business, the fear of any changes, when the stability of the result is more important than further development. The analysis of the process of working on the project from the stage of initiation to completion was carried out, the most problematic, bottlenecks in the current project management system were identified. Based on the conducted research, the company's management has developed and approved a plan for the development of CSU for the next year and for the future.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信