深基坑墙的岩土工程勘察与静力分析——以华沙地铁站建设为例

M. Mitew-Czajewska
{"title":"深基坑墙的岩土工程勘察与静力分析——以华沙地铁站建设为例","authors":"M. Mitew-Czajewska","doi":"10.1515/sggw-2015-0022","DOIUrl":null,"url":null,"abstract":"Abstract The paper presents detailed analysis of the case – a construction of deep excavation of metro station in Warsaw. Basing on this example, the great impact of the accuracy of the geotechnical investigation on the static analysis of diaphragm walls is discussed. Geotechnical studies for the construction of the central section of the second metro line were carried out in stages. Basic geotechnical soil investigation took place in the first stage of investment process, e.g. building permit and tender design stages in 2003–2004, 2007 and 2010. In subsequent years, complementary soil investigations have been performed by the contractor, and the results occurred to differ significantly. In the first part of the paper detailed description of the case is introduced. The geological conditions in the area of the station and the interpretation of the results of the three successive stages of geotechnical investigation are presented. As a result, two locations were selected with a great diversity of the soil profile depending on the stage of investigation. For each location, detailed, multiple static analysis of diaphragm walls were performed, taking into account changes in the soil profile. In the paper, one selected location is described in detail. The discussion of calculation results for this location in relation to the changing geotechnical data is presented and final conclusions are provided.","PeriodicalId":169511,"journal":{"name":"Annals of Warsaw University of Life Sciences, Land Reclamation","volume":"116 24","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2015-06-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"6","resultStr":"{\"title\":\"Geotechnical investigation and static analysis of deep excavation walls – a case study of metro station construction in Warsaw\",\"authors\":\"M. Mitew-Czajewska\",\"doi\":\"10.1515/sggw-2015-0022\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Abstract The paper presents detailed analysis of the case – a construction of deep excavation of metro station in Warsaw. Basing on this example, the great impact of the accuracy of the geotechnical investigation on the static analysis of diaphragm walls is discussed. Geotechnical studies for the construction of the central section of the second metro line were carried out in stages. Basic geotechnical soil investigation took place in the first stage of investment process, e.g. building permit and tender design stages in 2003–2004, 2007 and 2010. In subsequent years, complementary soil investigations have been performed by the contractor, and the results occurred to differ significantly. In the first part of the paper detailed description of the case is introduced. The geological conditions in the area of the station and the interpretation of the results of the three successive stages of geotechnical investigation are presented. As a result, two locations were selected with a great diversity of the soil profile depending on the stage of investigation. For each location, detailed, multiple static analysis of diaphragm walls were performed, taking into account changes in the soil profile. In the paper, one selected location is described in detail. The discussion of calculation results for this location in relation to the changing geotechnical data is presented and final conclusions are provided.\",\"PeriodicalId\":169511,\"journal\":{\"name\":\"Annals of Warsaw University of Life Sciences, Land Reclamation\",\"volume\":\"116 24\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2015-06-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"6\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Annals of Warsaw University of Life Sciences, Land Reclamation\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1515/sggw-2015-0022\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Annals of Warsaw University of Life Sciences, Land Reclamation","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1515/sggw-2015-0022","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 6

摘要

摘要本文以华沙地铁车站深基坑施工为例进行了详细的分析。结合实例,论述了土工勘察精度对连续墙静力分析的重要影响。地铁二号线中段施工的岩土工程研究分阶段进行。在投资程序的第一阶段,例如2003-2004年、2007年和2010年的建筑许可证和投标设计阶段,进行了基本的岩土调查。在随后的几年中,承包商进行了补充土壤调查,结果出现了显着差异。论文的第一部分对案例进行了详细的描述。介绍了该站所在地区的地质条件,并对连续三个阶段的地质勘察结果进行了解释。因此,根据调查阶段的不同,选择了两个具有多种土壤剖面的地点。对于每个位置,考虑到土壤剖面的变化,对连续墙进行了详细的多次静力分析。本文对其中一个选定的地点进行了详细的描述。结合变化的岩土资料,对该位置的计算结果进行了讨论,并给出了最终结论。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Geotechnical investigation and static analysis of deep excavation walls – a case study of metro station construction in Warsaw
Abstract The paper presents detailed analysis of the case – a construction of deep excavation of metro station in Warsaw. Basing on this example, the great impact of the accuracy of the geotechnical investigation on the static analysis of diaphragm walls is discussed. Geotechnical studies for the construction of the central section of the second metro line were carried out in stages. Basic geotechnical soil investigation took place in the first stage of investment process, e.g. building permit and tender design stages in 2003–2004, 2007 and 2010. In subsequent years, complementary soil investigations have been performed by the contractor, and the results occurred to differ significantly. In the first part of the paper detailed description of the case is introduced. The geological conditions in the area of the station and the interpretation of the results of the three successive stages of geotechnical investigation are presented. As a result, two locations were selected with a great diversity of the soil profile depending on the stage of investigation. For each location, detailed, multiple static analysis of diaphragm walls were performed, taking into account changes in the soil profile. In the paper, one selected location is described in detail. The discussion of calculation results for this location in relation to the changing geotechnical data is presented and final conclusions are provided.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信