{"title":"A model for scheduling projects under the condition of inflation and under penalty and reward arrangements","authors":"J. Jolayemi","doi":"10.5784/17-0-191","DOIUrl":null,"url":null,"abstract":"A zero-one mixed integer linear programming model is developed for the scheduling of projects under the condition of inflation and under penalty and reward arrangements. The effects of inflation on time-cost trade-off curves are illustrated and a modified approach to time-cost trade-off analysis presented. Numerical examples are given to illustrate the model and its properties. The examples show that misleading schedules and inaccurate project-cost estimates will be produced if the inflation factor is neglected in an environment of high inflation. They also show that award of penalty or bonus is a catalyst for early completion of a project, just as it can be expected.","PeriodicalId":30587,"journal":{"name":"ORiON","volume":"50 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2014-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"ORiON","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5784/17-0-191","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
A zero-one mixed integer linear programming model is developed for the scheduling of projects under the condition of inflation and under penalty and reward arrangements. The effects of inflation on time-cost trade-off curves are illustrated and a modified approach to time-cost trade-off analysis presented. Numerical examples are given to illustrate the model and its properties. The examples show that misleading schedules and inaccurate project-cost estimates will be produced if the inflation factor is neglected in an environment of high inflation. They also show that award of penalty or bonus is a catalyst for early completion of a project, just as it can be expected.