A model for scheduling projects under the condition of inflation and under penalty and reward arrangements

ORiON Pub Date : 2014-01-01 DOI:10.5784/17-0-191
J. Jolayemi
{"title":"A model for scheduling projects under the condition of inflation and under penalty and reward arrangements","authors":"J. Jolayemi","doi":"10.5784/17-0-191","DOIUrl":null,"url":null,"abstract":"A zero-one mixed integer linear programming model is developed for the scheduling of projects under the condition of inflation and under penalty and reward arrangements. The effects of inflation on time-cost trade-off curves are illustrated and a modified approach to time-cost trade-off analysis presented. Numerical examples are given to illustrate the model and its properties. The examples show that misleading schedules and inaccurate project-cost estimates will be produced if the inflation factor is neglected in an environment of high inflation. They also show that award of penalty or bonus is a catalyst for early completion of a project, just as it can be expected.","PeriodicalId":30587,"journal":{"name":"ORiON","volume":"50 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2014-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"ORiON","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5784/17-0-191","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

A zero-one mixed integer linear programming model is developed for the scheduling of projects under the condition of inflation and under penalty and reward arrangements. The effects of inflation on time-cost trade-off curves are illustrated and a modified approach to time-cost trade-off analysis presented. Numerical examples are given to illustrate the model and its properties. The examples show that misleading schedules and inaccurate project-cost estimates will be produced if the inflation factor is neglected in an environment of high inflation. They also show that award of penalty or bonus is a catalyst for early completion of a project, just as it can be expected.
通货膨胀条件下奖惩安排下的项目调度模型
针对膨胀条件下和奖惩安排下的项目调度问题,建立了一个0 - 1混合整数线性规划模型。本文阐述了通货膨胀对时间成本权衡曲线的影响,并提出了一种改进的时间成本权衡分析方法。数值算例说明了该模型及其性质。这些例子表明,如果在高通货膨胀的环境中忽视通货膨胀因素,将产生误导性的时间表和不准确的项目成本估计。他们还表明,奖励惩罚或奖金是项目提前完成的催化剂,正如可以预期的那样。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
11
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信