{"title":"The Rupture of an External Tendon in Île de Ré Bridge: Diagnosis, Safety Measures and Management","authors":"Bruno Godart Eng., Champs-sur-Marne, Luciano Tosini Eng., Laurent Gaillet Dr, Bouguenais, Mathieu Barbot Eng.","doi":"10.1080/10168664.2024.2341933","DOIUrl":null,"url":null,"abstract":"Ré Island Bridge connects Île de Ré to the mainland on the west coast of France and crosses four navigable sea passes, with a maximum air clearance of 30 m above sea level. This bridge is 2926 m lo...","PeriodicalId":51281,"journal":{"name":"Structural Engineering International","volume":"55 1","pages":""},"PeriodicalIF":1.1000,"publicationDate":"2024-07-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Structural Engineering International","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.1080/10168664.2024.2341933","RegionNum":4,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"CONSTRUCTION & BUILDING TECHNOLOGY","Score":null,"Total":0}
引用次数: 0
Abstract
Ré Island Bridge connects Île de Ré to the mainland on the west coast of France and crosses four navigable sea passes, with a maximum air clearance of 30 m above sea level. This bridge is 2926 m lo...
期刊介绍:
The aim of the Association is to exchange knowledge and to advance the practice of structural engineering worldwide in the service of the profession and society.