Omid Kebriyaii, Ali Heidari, Mohammad Khalilzadeh, Dragan Pamucar
{"title":"A green project scheduling with material ordering problem considering cost constraints and quality of materials","authors":"Omid Kebriyaii, Ali Heidari, Mohammad Khalilzadeh, Dragan Pamucar","doi":"10.1108/ecam-01-2024-0004","DOIUrl":null,"url":null,"abstract":"<h3>Purpose</h3>\n<p>Integrating project scheduling and material ordering problems is vital in realistically estimating project cost and duration. Also, the quality level of materials is important as one of the key project success factors.</p><!--/ Abstract__block -->\n<h3>Design/methodology/approach</h3>\n<p>In this paper, a three-objective mathematical model is presented for green project scheduling with materials ordering problems considering rental resources. The first objective is to minimize the total cost of the project site and logistics. The second objective is to minimize the environmental impacts of producing materials and the third objective is to maximize the total quality of materials. Since costs trigger several challenges in projects, cost constraints are considered in this model for the first time and also the cost of delay in supplying of materials by the suppliers has been deducted from the project costs. Subsequently, the model was implemented in a real case and solved by the Lagrangian Relaxation algorithm as an exact method on GAMS software for model validation.</p><!--/ Abstract__block -->\n<h3>Findings</h3>\n<p>Based on sensitivity analysis of some parameters, the findings indicate that the cost constraint and lead time have considerable effects on the project duration. Also, integrating project scheduling and material ordering improves the robustness of the project schedule.</p><!--/ Abstract__block -->\n<h3>Originality/value</h3>\n<p>The primary contributions of the present research can be stated as follows: considering the cost constraints in the project scheduling with material ordering problem, incorporating the rental resources and taking the quality levels of materials as well as the environmental impacts into account.</p><!--/ Abstract__block -->","PeriodicalId":11888,"journal":{"name":"Engineering, Construction and Architectural Management","volume":"21 1","pages":""},"PeriodicalIF":3.6000,"publicationDate":"2024-06-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering, Construction and Architectural Management","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.1108/ecam-01-2024-0004","RegionNum":2,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 0
Abstract
Purpose
Integrating project scheduling and material ordering problems is vital in realistically estimating project cost and duration. Also, the quality level of materials is important as one of the key project success factors.
Design/methodology/approach
In this paper, a three-objective mathematical model is presented for green project scheduling with materials ordering problems considering rental resources. The first objective is to minimize the total cost of the project site and logistics. The second objective is to minimize the environmental impacts of producing materials and the third objective is to maximize the total quality of materials. Since costs trigger several challenges in projects, cost constraints are considered in this model for the first time and also the cost of delay in supplying of materials by the suppliers has been deducted from the project costs. Subsequently, the model was implemented in a real case and solved by the Lagrangian Relaxation algorithm as an exact method on GAMS software for model validation.
Findings
Based on sensitivity analysis of some parameters, the findings indicate that the cost constraint and lead time have considerable effects on the project duration. Also, integrating project scheduling and material ordering improves the robustness of the project schedule.
Originality/value
The primary contributions of the present research can be stated as follows: considering the cost constraints in the project scheduling with material ordering problem, incorporating the rental resources and taking the quality levels of materials as well as the environmental impacts into account.
期刊介绍:
ECAM publishes original peer-reviewed research papers, case studies, technical notes, book reviews, features, discussions and other contemporary articles that advance research and practice in engineering, construction and architectural management. In particular, ECAM seeks to advance integrated design and construction practices, project lifecycle management, and sustainable construction. The journal’s scope covers all aspects of architectural design, design management, construction/project management, engineering management of major infrastructure projects, and the operation and management of constructed facilities. ECAM also addresses the technological, process, economic/business, environmental/sustainability, political, and social/human developments that influence the construction project delivery process.
ECAM strives to establish strong theoretical and empirical debates in the above areas of engineering, architecture, and construction research. Papers should be heavily integrated with the existing and current body of knowledge within the field and develop explicit and novel contributions. Acknowledging the global character of the field, we welcome papers on regional studies but encourage authors to position the work within the broader international context by reviewing and comparing findings from their regional study with studies conducted in other regions or countries whenever possible.