TIME AND COST EFFICIENCY ANALYSIS OF ACEH TENGAH REGENCY POM WORKSHOP PROJECT: A CRITICAL PATH METHOD APPROACH

Hafnidar A Rani, Fida Filaya Maina, Muhammad Shafly Aqsha, Muhammad Hafidz Mubarak
{"title":"TIME AND COST EFFICIENCY ANALYSIS OF ACEH TENGAH REGENCY POM WORKSHOP PROJECT: A CRITICAL PATH METHOD APPROACH","authors":"Hafnidar A Rani, Fida Filaya Maina, Muhammad Shafly Aqsha, Muhammad Hafidz Mubarak","doi":"10.29121/ijoest.v8.i3.2024.604","DOIUrl":null,"url":null,"abstract":"The study addresses construction delays in the Aceh Tengah Regency POM Workshop project, valued at IDR 6,414,000,000 and spanning approximately 1,507 m2 across two floors. Motivated by the need for a comprehensive understanding of activity relationships and critical paths, the research aims to assess project duration, costs, and efficiency. Employing the Critical Path Method (CPM) due to data constraints, the study elucidates activity dependencies, network planning, and critical paths. Data collected from relevant stakeholders include schedule and cost budget plans. The analysis reveals a potential acceleration of 21 days, reducing the project duration from 126 to 105 days with a 99.74% probability. Cost control indicates an escalation to IDR 6,949,573,170.20 after calculating direct costs, with a daily increase of 0.92%. The findings underscore the significance of CPM in project management, offering insights into optimizing timelines and costs. The study highlights the importance of efficient project management methodologies in addressing construction delays and managing project budgets effectively.","PeriodicalId":331301,"journal":{"name":"International Journal of Engineering Science Technologies","volume":"53 10","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-05-21","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Engineering Science Technologies","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29121/ijoest.v8.i3.2024.604","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The study addresses construction delays in the Aceh Tengah Regency POM Workshop project, valued at IDR 6,414,000,000 and spanning approximately 1,507 m2 across two floors. Motivated by the need for a comprehensive understanding of activity relationships and critical paths, the research aims to assess project duration, costs, and efficiency. Employing the Critical Path Method (CPM) due to data constraints, the study elucidates activity dependencies, network planning, and critical paths. Data collected from relevant stakeholders include schedule and cost budget plans. The analysis reveals a potential acceleration of 21 days, reducing the project duration from 126 to 105 days with a 99.74% probability. Cost control indicates an escalation to IDR 6,949,573,170.20 after calculating direct costs, with a daily increase of 0.92%. The findings underscore the significance of CPM in project management, offering insights into optimizing timelines and costs. The study highlights the importance of efficient project management methodologies in addressing construction delays and managing project budgets effectively.
Aceh Tengah Regency POM 车间项目的时间和成本效益分析:关键路径法
本研究探讨了亚齐登嘉地区 POM 车间项目的施工延误问题,该项目价值 64.14 亿印尼盾,占地约 1,507 平方米,共两层。出于全面了解活动关系和关键路径的需要,该研究旨在评估项目工期、成本和效率。由于数据限制,研究采用了关键路径法(CPM),阐明了活动依赖关系、网络规划和关键路径。从相关利益方收集的数据包括进度和成本预算计划。分析表明,有可能加快 21 天,将项目工期从 126 天缩短到 105 天,概率为 99.74%。成本控制显示,在计算直接成本后,成本上升至 6,949,573,170.20 印尼盾,日增幅为 0.92%。研究结果凸显了 CPM 在项目管理中的重要性,为优化时间安排和成本提供了启示。研究强调了高效项目管理方法在解决施工延误和有效管理项目预算方面的重要性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信