SOLAR POWERED OFF-GRID WATER DISTRIBUTION PROJECTS: A CASE STUDY COMPARISON OF TWO COMMUNITIES

Lonny Simonian, Paul Redden
{"title":"SOLAR POWERED OFF-GRID WATER DISTRIBUTION PROJECTS: A CASE STUDY COMPARISON OF TWO COMMUNITIES","authors":"Lonny Simonian, Paul Redden","doi":"10.14455/isec.2024.11(1).epe-12","DOIUrl":null,"url":null,"abstract":"This paper presents the pre-construction planning and construction installation phases of student-run projects in Ecuador and Ghana to provide fresh water via pumped water storage through photovoltaic (PV) systems. Our Ecuadorian project relied on a preliminary design prepared by a non-profit organization as the construction basis. The Ghanian project was designed by students, with faculty support. These two case studies were chosen because they had similar project goals, occurred close in time, and had the same faculty and student clubs performing the work. The fundamental project management areas of scope, schedule, and budget management were assessed as a basis for comparison. Although there were several differences between the projects, students gained new knowledge in all of these areas. The work involved several students and two faculty from California Polytechnic State University, San Luis Obispo (Cal Poly). The work included piping connections to direct current submersible pumps, water storage, distribution piping/connections to a village community center or directly to households, PV panels, and an electrical distribution system with overcurrent protection. The initial design was an important part of each project; however, many details were resolved during construction using a design-build approach.","PeriodicalId":477265,"journal":{"name":"Proceedings of International Structural Engineering and Construction","volume":"522 2","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-03-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of International Structural Engineering and Construction","FirstCategoryId":"0","ListUrlMain":"https://doi.org/10.14455/isec.2024.11(1).epe-12","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

This paper presents the pre-construction planning and construction installation phases of student-run projects in Ecuador and Ghana to provide fresh water via pumped water storage through photovoltaic (PV) systems. Our Ecuadorian project relied on a preliminary design prepared by a non-profit organization as the construction basis. The Ghanian project was designed by students, with faculty support. These two case studies were chosen because they had similar project goals, occurred close in time, and had the same faculty and student clubs performing the work. The fundamental project management areas of scope, schedule, and budget management were assessed as a basis for comparison. Although there were several differences between the projects, students gained new knowledge in all of these areas. The work involved several students and two faculty from California Polytechnic State University, San Luis Obispo (Cal Poly). The work included piping connections to direct current submersible pumps, water storage, distribution piping/connections to a village community center or directly to households, PV panels, and an electrical distribution system with overcurrent protection. The initial design was an important part of each project; however, many details were resolved during construction using a design-build approach.
太阳能离网输水项目:两个社区的案例研究比较
本文介绍了厄瓜多尔和加纳由学生运营的项目的施工前规划和施工安装阶段,该项目通过光伏(PV)系统抽水蓄能提供淡水。厄瓜多尔项目以非营利组织的初步设计为施工基础。加纳项目则是在教师的支持下由学生设计的。之所以选择这两个案例研究,是因为它们的项目目标相似,时间相近,并且由相同的教师和学生社团来完成工作。作为比较的基础,对范围、进度和预算管理等基本项目管理领域进行了评估。虽然项目之间存在一些差异,但学生们在所有这些领域都获得了新知识。加州州立理工大学圣路易斯奥比斯波分校(Cal Poly)的几名学生和两名教师参与了这项工作。工程包括直流潜水泵的管道连接、储水、通往村社区中心或直接通往住户的配水管道/连接、光伏电池板以及带过流保护的配电系统。最初的设计是每个项目的重要组成部分;然而,许多细节都是在采用设计-建造方法的施工过程中解决的。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信