{"title":"Analisis Optimasi Penjadwalan dengan Metode Precedence Diagram Method pada Proyek Konstruksi Pembangunan Rumah Sakit Regina Maris Medan","authors":"M. Rizky, A. P. M. Tarigan, G. C. Hasibuan","doi":"10.46799/jsa.v5i1.981","DOIUrl":null,"url":null,"abstract":"Good project management in the process of implementing private residential buildings, private buildings, and infrastructure buildings intended for the public interest, is one of the factors for the progress of a country. The study focused on the construction of the Regina Maris hospital in Medan, which is one of the developments in the complex category. The purpose of this study is to provide the results of an analysis of the development in order to achieve goals or targets that can provide efficient use of time, cost and quality which are considered to be the main supporting factors in a development.The research was carried out with three main activity stages, namely the identification stage, the data compilation stage and problem analysis and the use of the Precedence Diagram Method (PDM) method to analyze the optimization of work implementation schedules. The identification stage was carried out in the study area, beginning with observing the condition of the construction implementation, and deepening the identification of environmental conditions or internal/external factors that could hinder work. The results of the identification stage, accompanied by identification of problems and factors that can hinder work, are then used as initial data from the preparation stage of optimizing work implementation schedules using the Precedence Diagram Method \n \n ","PeriodicalId":509174,"journal":{"name":"Jurnal Syntax Admiration","volume":"12 4","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Syntax Admiration","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.46799/jsa.v5i1.981","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
Good project management in the process of implementing private residential buildings, private buildings, and infrastructure buildings intended for the public interest, is one of the factors for the progress of a country. The study focused on the construction of the Regina Maris hospital in Medan, which is one of the developments in the complex category. The purpose of this study is to provide the results of an analysis of the development in order to achieve goals or targets that can provide efficient use of time, cost and quality which are considered to be the main supporting factors in a development.The research was carried out with three main activity stages, namely the identification stage, the data compilation stage and problem analysis and the use of the Precedence Diagram Method (PDM) method to analyze the optimization of work implementation schedules. The identification stage was carried out in the study area, beginning with observing the condition of the construction implementation, and deepening the identification of environmental conditions or internal/external factors that could hinder work. The results of the identification stage, accompanied by identification of problems and factors that can hinder work, are then used as initial data from the preparation stage of optimizing work implementation schedules using the Precedence Diagram Method
在实施私人住宅建筑、私人建筑和公共利益基础设施建筑的过程中,良好的项目管理是一个国家进步的因素之一。本研究的重点是位于棉兰的 Regina Maris 医院的建设情况,该医院属于综合类开发项目之一。本研究的目的是提供对开发项目的分析结果,以实现能够有效利用时间、成本和质量的目标或指标,而时间、成本和质量被认为是开发项目的主要支持因素。研究主要通过三个活动阶段进行,即识别阶段、数据汇编阶段和问题分析,并使用先行图法(PDM)分析工作实施计划的优化。识别阶段在研究区域内进行,从观察施工实施情况开始,深入识别可能阻碍施工的环境条件或内部/外部因素。然后,将识别阶段的结果以及可能阻碍施工的问题和因素作为准备阶段的初始数据,使用先行图法优化施工进度计划。