Network Planning Analysis Using The Critical Path Method (CPM) as an Evaluation Tool for Project Planning and Control (Case Study of a Residential House Development Project in Pare City, Kediri Regency)

Dwi Husnul Rahmat, Ida Ayu Nuh Kartini
{"title":"Network Planning Analysis Using The Critical Path Method (CPM) as an Evaluation Tool for Project Planning and Control (Case Study of a Residential House Development Project in Pare City, Kediri Regency)","authors":"Dwi Husnul Rahmat, Ida Ayu Nuh Kartini","doi":"10.30996/jem17.v8i2.9905","DOIUrl":null,"url":null,"abstract":"The construction of residential houses in Pare City Kediri Regency experienced problems in the construction process was late from the predetermined schedule, which resulted in increased costs incurred. This project is located in Pare City, Kediri Regency, on a land area of 1200 M² with a size of 120 x 10 M first construction is a 20 x 8 M residential house. According to the agreed plan and a master schedule, this project is expected to be completed within 80 working days, and every day only work for 8 hours reality the implementation of this project, various factors affect the progress of the work. The percentage of actual cumulative progress until the 4th week of January is 97.42% of the 100% master schedule plan, there is a deviation of 2. 58 & it can be seen that the achievement of progress from the previous month indicates a continuous delay from the monthly plans made. One of the methods that must be used to design Network Planning is the Critical Path Method (CPM). The CPM method is used to plan, schedule, and control project activities that are deterministic or single time after evaluation data is obtained so that time and cost are more efficient and effective in calculating evaluation data using the CPM method. The project, which was initially completed in 103 days at Rp. 213,956,500 after being evaluated, and if there were no mistakes during project implementation, the normal time was 72 days at Rp. 160,276. 500 and then using the CPM method obtained an effective time of 52 days and an efficiency cost of Rp. 115,755,240. Keywords: Critical path method (CPM), Network Planning, Acceleration, Time, Cost.","PeriodicalId":431079,"journal":{"name":"JEM17: Jurnal Ekonomi Manajemen","volume":"130 ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-11-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"JEM17: Jurnal Ekonomi Manajemen","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30996/jem17.v8i2.9905","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The construction of residential houses in Pare City Kediri Regency experienced problems in the construction process was late from the predetermined schedule, which resulted in increased costs incurred. This project is located in Pare City, Kediri Regency, on a land area of 1200 M² with a size of 120 x 10 M first construction is a 20 x 8 M residential house. According to the agreed plan and a master schedule, this project is expected to be completed within 80 working days, and every day only work for 8 hours reality the implementation of this project, various factors affect the progress of the work. The percentage of actual cumulative progress until the 4th week of January is 97.42% of the 100% master schedule plan, there is a deviation of 2. 58 & it can be seen that the achievement of progress from the previous month indicates a continuous delay from the monthly plans made. One of the methods that must be used to design Network Planning is the Critical Path Method (CPM). The CPM method is used to plan, schedule, and control project activities that are deterministic or single time after evaluation data is obtained so that time and cost are more efficient and effective in calculating evaluation data using the CPM method. The project, which was initially completed in 103 days at Rp. 213,956,500 after being evaluated, and if there were no mistakes during project implementation, the normal time was 72 days at Rp. 160,276. 500 and then using the CPM method obtained an effective time of 52 days and an efficiency cost of Rp. 115,755,240. Keywords: Critical path method (CPM), Network Planning, Acceleration, Time, Cost.
使用关键路径法(CPM)进行网络规划分析,作为项目规划和控制的评估工具(克迭里省帕雷市住宅开发项目案例研究)
Pare City Kediri Regency 的住宅建设在施工过程中遇到了一些问题,比预定的工期晚了,导致成本增加。该项目位于克迪里省帕雷市,占地面积为 1200 平方米,建筑面积为 120 x 10 平方米,首先建造的是 20 x 8 平方米的住宅。根据商定的计划和总进度表,该项目预计在 80 个工作日内完工,每天只工作 8 个小时 现实中,该项目实施过程中,各种因素影响着工程进度。截至 1 月第 4 周,实际累计进度占总进度计划 100%的 97.42%,偏差为 2.58%,可以看出,从上个月的进度完成情况来看,与制定的月度计划相比,进度持续延迟。设计网络规划必须使用的方法之一是关键路径法(CPM)。CPM 方法是在获得评估数据后,对确定性或单一时间的项目活动进行计划、进度安排和控制,这样在使用 CPM 方法计算评估数据时,时间和成本的效率更高,效果更好。该项目经评估后,最初完成时间为 103 天,费用为 213,956,500 印尼盾,如果在项目实施过程中不出现任何失误,正常时间为 72 天,费用为 160,276,500 印尼盾,而使用 CPM 方法后,有效时间为 52 天,有效成本为 115,755,240 印尼盾。 关键词关键路径法(CPM)、网络规划、加速、时间、成本。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信