{"title":"IDENTIFIKASI WASTE PROYEK INFRASTRUKTUR TRANSMISI LISTRIK DENGAN VALUE STREAM MAPPING","authors":"Grace Simamora, Mona F Toyfur, None Heni Fitriani","doi":"10.24912/jmts.v6i2.21179","DOIUrl":null,"url":null,"abstract":"Based on the performance report of the Directorate General of Electricity 2020, the percentage of performance achievements in adding electric power transmission is 58,17%. The electricity transmission project itself is a complex project because it consists of many stages of work that are interrelated with each other, spread over many locations and involve many stakeholders. This type of project is generally difficult to control and contributes a lot of activities that should not be needed (waste) which leads to delays in project completion. The purpose of this study is to identify waste based on the concept of lean construction in power transmission projects. The research was conducted in the 500 kV Sumatera Package 3 transmission project and was descriptive qualitative as measured by quantitative methods. The research begins with taking actual data in the field with working papers filled out by each personnel related to the work to be mapped. Existing waste is obtained from mapping carried out using lean construction Value Stream Mapping (VSM) tools. The results show that the largest waste in the Transmission project is waste Waiting with an average of 2,29 and the lowest waste is Inventory with an average of 0,14 with the order of the largest waste to the smallest waste, namely Waiting, Defects, Overprocessing, Motion, Overproduction, Transportation, and Inventory. Abstrak Berdasarkan laporan kinerja Ditjen ketenagalistrikan 2020, persentase capaian kinerja penambahan transmisi tenaga listrik adalah 58,17%. Proyek transmisi listrik sendiri merupakan proyek yang kompleks karena terdiri dari banyak tahapan pekerjaan yang saling berkaitan satu sama lain, terpencar pada banyak lokasi serta melibatkan banyak stakeholder. Tipe proyek seperti ini pada umumnya sulit dikontrol dan menyumbangkan banyak aktivitas yang seharusnya tidak diperlukan (waste) yang berujung kepada keterlambatan penyelesaian proyek. Tujuan dari penelitian ini adalah untuk mengidentifikasi pemborosan (waste) berdasarkan konsep lean construction pada proyek transmisi listrik. Penelitian dilakukan di proyek transmisi 500 kV Sumatera Paket 3 dan bersifat deskriptif kualitatif yang diukur dengan metode kuantitatif. Penelitian dimulai dengan pengambilan data aktual di lapangan dengan kertas kerja yang diisi masing-masing personil yang berkaitan dengan pekerjaan yang akan dipetakan. Pemborosan (waste) eksisting diperoleh dari pemetaan yang dilakukan dengan tools lean construction Value Stream Mapping (VSM). Hasil penelitian menunjukkan bahwa pemborosan (waste) terbesar pada proyek transmisi adalah Waiting dengan rata-rata sebesar 2,29 dan waste terrendah adalah Inventory dengan rata-rata 0,14 dengan urutan waste terbesar ke terkecil yaitu Waiting, Defects, Overprocessing, Motion, Overproduction, Transportation dan Inventory.","PeriodicalId":493953,"journal":{"name":"Jurnal Mitra Teknik Sipil","volume":"16 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-05-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Mitra Teknik Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24912/jmts.v6i2.21179","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
Based on the performance report of the Directorate General of Electricity 2020, the percentage of performance achievements in adding electric power transmission is 58,17%. The electricity transmission project itself is a complex project because it consists of many stages of work that are interrelated with each other, spread over many locations and involve many stakeholders. This type of project is generally difficult to control and contributes a lot of activities that should not be needed (waste) which leads to delays in project completion. The purpose of this study is to identify waste based on the concept of lean construction in power transmission projects. The research was conducted in the 500 kV Sumatera Package 3 transmission project and was descriptive qualitative as measured by quantitative methods. The research begins with taking actual data in the field with working papers filled out by each personnel related to the work to be mapped. Existing waste is obtained from mapping carried out using lean construction Value Stream Mapping (VSM) tools. The results show that the largest waste in the Transmission project is waste Waiting with an average of 2,29 and the lowest waste is Inventory with an average of 0,14 with the order of the largest waste to the smallest waste, namely Waiting, Defects, Overprocessing, Motion, Overproduction, Transportation, and Inventory. Abstrak Berdasarkan laporan kinerja Ditjen ketenagalistrikan 2020, persentase capaian kinerja penambahan transmisi tenaga listrik adalah 58,17%. Proyek transmisi listrik sendiri merupakan proyek yang kompleks karena terdiri dari banyak tahapan pekerjaan yang saling berkaitan satu sama lain, terpencar pada banyak lokasi serta melibatkan banyak stakeholder. Tipe proyek seperti ini pada umumnya sulit dikontrol dan menyumbangkan banyak aktivitas yang seharusnya tidak diperlukan (waste) yang berujung kepada keterlambatan penyelesaian proyek. Tujuan dari penelitian ini adalah untuk mengidentifikasi pemborosan (waste) berdasarkan konsep lean construction pada proyek transmisi listrik. Penelitian dilakukan di proyek transmisi 500 kV Sumatera Paket 3 dan bersifat deskriptif kualitatif yang diukur dengan metode kuantitatif. Penelitian dimulai dengan pengambilan data aktual di lapangan dengan kertas kerja yang diisi masing-masing personil yang berkaitan dengan pekerjaan yang akan dipetakan. Pemborosan (waste) eksisting diperoleh dari pemetaan yang dilakukan dengan tools lean construction Value Stream Mapping (VSM). Hasil penelitian menunjukkan bahwa pemborosan (waste) terbesar pada proyek transmisi adalah Waiting dengan rata-rata sebesar 2,29 dan waste terrendah adalah Inventory dengan rata-rata 0,14 dengan urutan waste terbesar ke terkecil yaitu Waiting, Defects, Overprocessing, Motion, Overproduction, Transportation dan Inventory.
根据电力总局2020年的业绩报告,增加电力传输的业绩成就百分比为58.17%。输电工程本身是一个复杂的工程,因为它包括许多相互关联的工作阶段,分布在许多地点,涉及许多利益相关者。这种类型的项目通常难以控制,并且会产生许多本不需要的活动(浪费),从而导致项目完成的延迟。本研究的目的是基于精益建设的理念来识别输电工程中的浪费。本研究是在500千伏苏门答腊3包输电工程中进行的,采用定量方法进行描述性定性研究。这项研究首先在实地获取实际数据,并由与要绘制的工作有关的每个人员填写工作底稿。现有的浪费是通过使用精益建筑价值流映射(VSM)工具进行的映射获得的。结果表明:变速器项目中最大的浪费是等待浪费,平均为2.29;最小的浪费是库存浪费,平均为0.14。浪费从大到小依次为等待浪费、缺陷浪费、过度加工浪费、运动浪费、生产过剩浪费、运输浪费、库存浪费。[摘要]Berdasarkan laporan kinerja Ditjen ketenagalistrikan 2020,代表队长kinerja penambahan传输tenagalistrik adalah 58,17%。Proyek传播上市公司sendiri merupakan Proyek yang kompleks karena terdiri dari banyak tahapan pekerjaan yang销售berkaitan satu sama lain, terpenar padbanyak lokasi serta melibatkan banyak利益相关者。Tipe proyek seperti ini pada umumnya sulit dikontrol dan menyumbangkan banyak aktivitas yang seharusnya tidak diperlukan(废物)yang berujung kepada keterlambatan penyelesesan proyek。Tujuan dari penelitian ini adalah untuk mengidentifikasi pemborosan(废物)berdasarkan konsep精益建设方案传输清单。Penelitian dilakkan diyek输电500kv苏门答腊Paket 3号线路的质量描述杨diokur dengan方法的定量。Penelitian dimulai dengan pengambilan数据实际di lapangan dengan kertas kerja yang diisi测量人员yang berkaitan dengan pekerjaan yang akan dipetakan。废铁(废铁),废铁(废铁),废铁(废铁),废铁(废铁),废铁(废铁),废铁(废铁),废铁(废铁),废铁(废铁),废铁(废铁),废铁(废铁)。Hasil penelitian menunjukkan bahwa pemborosan(废物)terbesar pada proyek传输adalah等待dengan - rata-rata sebesar 2,29个废物terendan -rata库存dengan -rata库存dengan -rata库存,14个dengan - urutan废物terbesar -rata库存等待,缺陷,过度加工,运动,生产过剩,运输丹库存。