Professionals’ Perceptions on Construction Progress Measurement Methods Used in Ghana

J. Danku, K. Agyekum, F. Asare
{"title":"Professionals’ Perceptions on Construction Progress Measurement Methods Used in Ghana","authors":"J. Danku, K. Agyekum, F. Asare","doi":"10.4236/wjet.2020.82012","DOIUrl":null,"url":null,"abstract":"Progress measurement is cardinal for effective project delivery. It assesses the physical amount of completed work within budgeted cost and manpower performance at a specified stage of the project. Effective progress measurement facilitates progress monitoring, an inevitability for identifying early warning signs and confirmation of structured work proceeding. Different progress measuring methods are available and used for construction projects. They range from the traditional to the contemporary ones like three-dimensional and four-dimensional models. This paper examines current progress measurement methods used in the Ghanaian construction industry. Eight commonly employed methods were identified from the literature and rated by sixty-two construction professionals, practicing with tier one construction firms and construction consultancy services. Relative Important Index ranking and Mann-Whitney U test statistics were used to rank and check the consistency of survey responses. Cost Ratio ranked the highest, followed by Supervisor’s Opinion and Units Completed. The fourth-ranked method was Time Ratio, then Incremental Milestone before Start-Finish. Weighted/Equivalent Units was at the penultimate with Earned Value Analysis ranked the lowest. The study will not only underscore the relevance of the current project progress measurement practices and provoke prolific debates on their merits, but will also serve as a precursor for critical evaluation of the methods with the view to identifying barriers militating against realistic progress assessment of construction works.","PeriodicalId":344331,"journal":{"name":"World Journal of Engineering and Technology","volume":"9 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-03-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"World Journal of Engineering and Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4236/wjet.2020.82012","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Progress measurement is cardinal for effective project delivery. It assesses the physical amount of completed work within budgeted cost and manpower performance at a specified stage of the project. Effective progress measurement facilitates progress monitoring, an inevitability for identifying early warning signs and confirmation of structured work proceeding. Different progress measuring methods are available and used for construction projects. They range from the traditional to the contemporary ones like three-dimensional and four-dimensional models. This paper examines current progress measurement methods used in the Ghanaian construction industry. Eight commonly employed methods were identified from the literature and rated by sixty-two construction professionals, practicing with tier one construction firms and construction consultancy services. Relative Important Index ranking and Mann-Whitney U test statistics were used to rank and check the consistency of survey responses. Cost Ratio ranked the highest, followed by Supervisor’s Opinion and Units Completed. The fourth-ranked method was Time Ratio, then Incremental Milestone before Start-Finish. Weighted/Equivalent Units was at the penultimate with Earned Value Analysis ranked the lowest. The study will not only underscore the relevance of the current project progress measurement practices and provoke prolific debates on their merits, but will also serve as a precursor for critical evaluation of the methods with the view to identifying barriers militating against realistic progress assessment of construction works.
专业人士对加纳使用的施工进度测量方法的看法
进度度量是有效项目交付的基础。它在项目的特定阶段评估在预算成本和人力绩效范围内完成工作的实际数量。有效的进度度量有助于进度监控,这是识别早期预警信号和确认结构化工作过程的必然性。建设项目的进度测量方法多种多样。它们的范围从传统的到现代的,如三维和四维模型。本文考察了目前在加纳建筑业中使用的进度测量方法。从文献中确定了八种常用的方法,并由62名与一级建筑公司和建筑咨询服务合作的建筑专业人员进行了评级。采用相对重要指数排序和Mann-Whitney U检验统计量对调查结果进行排序和一致性检验。成本比率排名最高,其次是主管意见和完成单位。排名第四的方法是时间比率,然后是开始-结束前的增量里程碑。加权/等效单位排名倒数第二,挣值分析排名最低。这项研究不仅将强调当前项目进度测量方法的相关性,并引发对其优点的激烈辩论,而且还将成为对这些方法进行批判性评估的先驱,以确定妨碍对建筑工程进行实际进度评估的障碍。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信