{"title":"Hydropower Development: Before and After 1992","authors":"R. Shrestha","doi":"10.3126/HN.V18I0.14638","DOIUrl":null,"url":null,"abstract":"Hydropower Development Policy promulgated in 1992 by Government of Nepal (GoN) heralded domestic and foreign private investment in hydropower projects, which was instrumental in adding 255,647 MW to the system with the investment of US$ 493 million in a period of 23 years. While, public sector succeeded to add only 238.6 MW during the same period; thus adding a total of 489.14 MW to the system by public and private sectors. As cumulative total installed capacity of projects implemented prior to it in eight decades from 1911 through 1991 was only 239.33 MW, it manifests successful implementation of the policy with resultant mobilization of private investment. Only 9th five-year plan period (1997-2002) succeeded to achieve 91% of the target set for the period resulting in mismatch in the growth of demand and supply; consequently load shedding. The reasons behind the failure need an in-depth analysis and critique of the policy and improvement thereof. HYDRO Nepal Journal of Water Energy and Environment Volume- 18, 2016, January Page -16 to 21","PeriodicalId":117617,"journal":{"name":"Hydro Nepal: Journal of Water, Energy and Environment","volume":"2 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2016-03-15","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"7","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Hydro Nepal: Journal of Water, Energy and Environment","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.3126/HN.V18I0.14638","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 7
Abstract
Hydropower Development Policy promulgated in 1992 by Government of Nepal (GoN) heralded domestic and foreign private investment in hydropower projects, which was instrumental in adding 255,647 MW to the system with the investment of US$ 493 million in a period of 23 years. While, public sector succeeded to add only 238.6 MW during the same period; thus adding a total of 489.14 MW to the system by public and private sectors. As cumulative total installed capacity of projects implemented prior to it in eight decades from 1911 through 1991 was only 239.33 MW, it manifests successful implementation of the policy with resultant mobilization of private investment. Only 9th five-year plan period (1997-2002) succeeded to achieve 91% of the target set for the period resulting in mismatch in the growth of demand and supply; consequently load shedding. The reasons behind the failure need an in-depth analysis and critique of the policy and improvement thereof. HYDRO Nepal Journal of Water Energy and Environment Volume- 18, 2016, January Page -16 to 21
尼泊尔政府1992年颁布的水电发展政策,鼓励国内外私人投资水电项目,在23年期间投资4.93亿美元,为该系统增加了255,647兆瓦。而同期,公共部门仅成功增加了238.6兆瓦;因此,公共和私营部门为该系统增加了489.14兆瓦的电力。从1911年到1991年的80年间,在此之前实施的项目累计总装机容量仅为239.33兆瓦,这表明政策的成功实施,从而调动了私人投资。只有第九个五年计划期间(1997-2002年)成功实现了该时期设定的目标的91%,导致需求和供应增长不匹配;因此,负载脱落。失败的原因需要对政策进行深入的分析和批判,并加以改进。hydronepal Journal of Water Energy and Environment vol . 18, 2016, January Page -16 - 21