A Supply Planning Model for Multilevel Assembly Systems Under Random Lead Times

F. Hnaien, A. Dolgui
{"title":"A Supply Planning Model for Multilevel Assembly Systems Under Random Lead Times","authors":"F. Hnaien, A. Dolgui","doi":"10.1109/ETFA.2006.355246","DOIUrl":null,"url":null,"abstract":"A multilevel assembly system with one type of finished product and several types of components is considered. The component lead times for components at each period are independent random variables, and the demand of finished product per period is constant. Finished products should be delivered by the end of each period. Otherwise a backlogging cost is incurred. Components necessary to assemble the same semi-finished product that are delivered in advance will cause holding cost. The objective is to find the optimal release dates (safety lead times which is measured in number of periods) for the components in order to minimize the total expected costs composed of the finished product backlogging cost and the component holding cost. We propose a model that gives the optimal release dates values for the components.","PeriodicalId":431393,"journal":{"name":"2006 IEEE Conference on Emerging Technologies and Factory Automation","volume":"42 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2006-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2006 IEEE Conference on Emerging Technologies and Factory Automation","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ETFA.2006.355246","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

A multilevel assembly system with one type of finished product and several types of components is considered. The component lead times for components at each period are independent random variables, and the demand of finished product per period is constant. Finished products should be delivered by the end of each period. Otherwise a backlogging cost is incurred. Components necessary to assemble the same semi-finished product that are delivered in advance will cause holding cost. The objective is to find the optimal release dates (safety lead times which is measured in number of periods) for the components in order to minimize the total expected costs composed of the finished product backlogging cost and the component holding cost. We propose a model that gives the optimal release dates values for the components.
随机交货期下多级装配系统的供应计划模型
考虑具有一种成品和几种部件的多级装配系统。各周期构件的交货期是独立的随机变量,各周期成品需求是恒定的。成品应在每个周期结束前交付。否则将产生积压成本。提前交付的相同半成品组装所需的部件将产生持有成本。目标是找到组件的最佳发布日期(以周期数衡量的安全提前期),以最小化由成品积压成本和组件持有成本组成的总预期成本。我们提出了一个模型,该模型给出了组件的最佳发布日期值。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信