A modified serial scheduling scheme for resource constrained project scheduling weighted earliness tardiness problem

Srijith Rajeev, S. Kurian, B. Paul
{"title":"A modified serial scheduling scheme for resource constrained project scheduling weighted earliness tardiness problem","authors":"Srijith Rajeev, S. Kurian, B. Paul","doi":"10.1504/IJIDS.2015.071373","DOIUrl":null,"url":null,"abstract":"This paper proposes a modified serial scheduling scheme for resource constrained project scheduling weighted earliness tardiness problem (RCPSPWET). Project activities are assumed to have known unit earliness and tardiness penalty cost and constant renewable resource requirements. The objective is to schedule the activities in such a way that it minimises the total weighted earliness-tardiness penalty cost of the project, subject to the precedence constraints and the constant renewable resource availability constraints. A modified serial scheduling scheme using a sliding factor is proposed along with a heuristic method for solving the RCPSPWET.","PeriodicalId":303039,"journal":{"name":"Int. J. Inf. Decis. Sci.","volume":"80 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2015-08-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"10","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Int. J. Inf. Decis. Sci.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1504/IJIDS.2015.071373","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 10

Abstract

This paper proposes a modified serial scheduling scheme for resource constrained project scheduling weighted earliness tardiness problem (RCPSPWET). Project activities are assumed to have known unit earliness and tardiness penalty cost and constant renewable resource requirements. The objective is to schedule the activities in such a way that it minimises the total weighted earliness-tardiness penalty cost of the project, subject to the precedence constraints and the constant renewable resource availability constraints. A modified serial scheduling scheme using a sliding factor is proposed along with a heuristic method for solving the RCPSPWET.
资源受限项目调度加权早延迟问题的改进串行调度方案
针对资源受限的项目调度加权早延迟问题,提出了一种改进的串行调度方案。假设项目活动具有已知的单位提前和延迟惩罚成本和恒定的可再生资源需求。目标是以这样一种方式来安排活动,使项目的总加权提前-延迟惩罚成本最小化,受制于优先约束和持续的可再生资源可用性约束。提出了一种基于滑动因子的改进串行调度方案,并提出了一种求解RCPSPWET的启发式方法。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信