Variations Order of Building Construction Project a Case from Nepal

Neetu Koirala
{"title":"Variations Order of Building Construction Project a Case from Nepal","authors":"Neetu Koirala","doi":"10.24321/2456.9925.202105","DOIUrl":null,"url":null,"abstract":"The main objective of this study is to identify the origin and causes of variation orders and their impacts in project cost and completion time for developing preventing measures which can be beneficial in upcoming similar projects. The study is conducted in project inside the Tribhuvan University premises, Kathmandu. The primary data were collected from the questionnaire survey and field study. A questionnaire survey was conducted with construction team who are related to the project. For the case study of the project, contract documents were obtained from the related offices which were thoroughly studied to obtain the project related findings about variation orders relating to project cost and completion time. Five ranking linkert scale have been used for ranking the perception based relative importance index of respondents about causes of variation orders. Existence of variation orders inside Tribhuvan University premises, Kathmandu has been noted from the study. 9.85%, 5.99%, 10.37%, 12.32% and 21.02% cost above the contract amount has been incurred at the completion of the projects respectively. Similarly, 26.67%, 83.33%, 12.5%, 20% and 25% time for the successive contract has been increased by the extension of the contract completion time. From the study, main causes of variation orders are known to be change of plan, change of scope, defect of bill of quantities, lack of specified and appropriate competent construction manager and impediment in prompt decision making. Similarly, causes of variation orders impacting project cost are additional work, client financial problems/ delay in payment of bill and change in design. Causes of variation orders impacting project time are change in design, delay in payment and dispute between parties to the contract. The control measures for the variation orders are appointment of project manager to supervise design, preparation of bill of quantities with good estimate and adequate financial planning. The findings of this study will be beneficial for developers, designers and contractors in building projects and also to the Governmental authorities to develop preventing measures to eliminate or reduce variation orders.","PeriodicalId":267306,"journal":{"name":"Journal of Advanced Research in Construction and Urban Architecture","volume":"14 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-05-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Advanced Research in Construction and Urban Architecture","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24321/2456.9925.202105","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

Abstract

The main objective of this study is to identify the origin and causes of variation orders and their impacts in project cost and completion time for developing preventing measures which can be beneficial in upcoming similar projects. The study is conducted in project inside the Tribhuvan University premises, Kathmandu. The primary data were collected from the questionnaire survey and field study. A questionnaire survey was conducted with construction team who are related to the project. For the case study of the project, contract documents were obtained from the related offices which were thoroughly studied to obtain the project related findings about variation orders relating to project cost and completion time. Five ranking linkert scale have been used for ranking the perception based relative importance index of respondents about causes of variation orders. Existence of variation orders inside Tribhuvan University premises, Kathmandu has been noted from the study. 9.85%, 5.99%, 10.37%, 12.32% and 21.02% cost above the contract amount has been incurred at the completion of the projects respectively. Similarly, 26.67%, 83.33%, 12.5%, 20% and 25% time for the successive contract has been increased by the extension of the contract completion time. From the study, main causes of variation orders are known to be change of plan, change of scope, defect of bill of quantities, lack of specified and appropriate competent construction manager and impediment in prompt decision making. Similarly, causes of variation orders impacting project cost are additional work, client financial problems/ delay in payment of bill and change in design. Causes of variation orders impacting project time are change in design, delay in payment and dispute between parties to the contract. The control measures for the variation orders are appointment of project manager to supervise design, preparation of bill of quantities with good estimate and adequate financial planning. The findings of this study will be beneficial for developers, designers and contractors in building projects and also to the Governmental authorities to develop preventing measures to eliminate or reduce variation orders.
建筑工程变更顺序——以尼泊尔为例
本研究的主要目的是确定变更订单的来源和原因,以及它们对项目成本和完工时间的影响,以便制定预防措施,这些措施可以在即将到来的类似项目中有益。这项研究是在加德满都特里布万大学房地内进行的项目。主要数据来源于问卷调查和实地调研。对与项目相关的施工队进行问卷调查。对于项目的案例研究,从相关部门获得合同文件,并对其进行了深入研究,以获得与项目成本和完工时间相关的变更订单的项目相关发现。五个排名链接量表已被用于排名基于感知的相对重要性指数的受访者关于变化顺序的原因。在加德满都Tribhuvan大学馆舍内存在变化顺序,从研究中已经注意到。工程竣工时已发生超过合同金额的费用分别为9.85%、5.99%、10.37%、12.32%和21.02%。同样,由于合同完成时间的延长,连续合同的26.67%、83.33%、12.5%、20%和25%的时间都增加了。从研究中得知,变更订单的主要原因是计划变更、范围变更、工程量清单缺陷、缺乏专门的、合适的施工主管以及决策不及时。同样,变更订单影响项目成本的原因是额外的工作、客户财务问题/延迟支付账单和设计变更。变更订单影响工程时间的原因有:设计变更、付款延迟、合同双方之间的纠纷。对变更单的控制措施是任命项目经理监督设计、编制工程量清单并做好预估、做好财务规划。这项研究的结果将有利于建筑项目的开发商、设计师和承包商,也有利于政府当局制定预防措施,以消除或减少变更订单。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信