E. Weinbrecht, D. Bloomquist, D. Mcdaniel, D. Tabor, J. W. Weed, T. Faturos, G. Mckee, P. J. Warner
{"title":"Status of the Z Refurbishment Project (ZR) at Sandia National Laboratories","authors":"E. Weinbrecht, D. Bloomquist, D. Mcdaniel, D. Tabor, J. W. Weed, T. Faturos, G. Mckee, P. J. Warner","doi":"10.1109/PPPS.2007.4345942","DOIUrl":null,"url":null,"abstract":"Sandia National Laboratories' Z Refurbishment (ZR) Project formally began in August 2002 to increase the Z Accelerator's utilization by providing the capability to perform more shots, improve precision and pulse shape variability, increase delivered current, and accomplish the improvements with minimal disruption to Z's ongoing programs. A project overview was provided at the 14th International Pulsed Power Conference in 2003 [1], This paper provides an update of the project including architectural changes over the past two years, timeframe for completion, and overall design and fabrication status.","PeriodicalId":200159,"journal":{"name":"2005 IEEE Pulsed Power Conference","volume":"52 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2007-06-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"6","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2005 IEEE Pulsed Power Conference","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/PPPS.2007.4345942","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 6
Abstract
Sandia National Laboratories' Z Refurbishment (ZR) Project formally began in August 2002 to increase the Z Accelerator's utilization by providing the capability to perform more shots, improve precision and pulse shape variability, increase delivered current, and accomplish the improvements with minimal disruption to Z's ongoing programs. A project overview was provided at the 14th International Pulsed Power Conference in 2003 [1], This paper provides an update of the project including architectural changes over the past two years, timeframe for completion, and overall design and fabrication status.