ALTERNATIF PEMECAHAN MASALAH KETERLAMBATANPENYELESAIAN PROYEK (STUDI KASUS PEMBANGUNAN GEDUNG PUSKESMAS LAREN KABUPATEN LAMONGAN)

Fridha Guivanny Putri, Rio Rahma Dana
{"title":"ALTERNATIF PEMECAHAN MASALAH KETERLAMBATANPENYELESAIAN PROYEK (STUDI KASUS PEMBANGUNAN GEDUNG PUSKESMAS LAREN KABUPATEN LAMONGAN)","authors":"Fridha Guivanny Putri, Rio Rahma Dana","doi":"10.30736/CVL.V3I2.260","DOIUrl":null,"url":null,"abstract":"The successfulness of executing the construction projects right on time is one of the most important goals both for the owners and contractors. In general, each construction project has a specific implementation plan and schedule of implementation. It contains some important things, for example when the project should begin, when it should be completed, and how to provide the resources. As in the development project of Public Health Center building in LarenDistrict, Lamongan Regency in 2016 which has been delayed up to six weeks, causing inaccuracy between the planningschedule anddevelopment implementation. This research aims to be used as an evaluation to get the fastest acceleration time by using cut and crashing method. From the data obtained fromthe time schedule, cost estimate plan (RAB),wage price analysis, and project materials,the next step is making the job network and determining the critical pathfor cut and crash method. The results of the study show that the project acceleration can be done up to 82 days or 7 days faster than the normal day, that is 89 days with acceleration cost of Rp. 347.935.000,00 or increased from the normal cost of Rp. 345.390.000,00. The percentage of the selected acceleration time ratio is approximately 6.02% faster than the normal time, while for the acceleration cost is approximately 0.68% greater than the normal cost. Therefore, with this research, the work actually can be completed on December 13, 2016.","PeriodicalId":426383,"journal":{"name":"Jurnal CIVILA","volume":"36 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-10-16","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal CIVILA","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30736/CVL.V3I2.260","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The successfulness of executing the construction projects right on time is one of the most important goals both for the owners and contractors. In general, each construction project has a specific implementation plan and schedule of implementation. It contains some important things, for example when the project should begin, when it should be completed, and how to provide the resources. As in the development project of Public Health Center building in LarenDistrict, Lamongan Regency in 2016 which has been delayed up to six weeks, causing inaccuracy between the planningschedule anddevelopment implementation. This research aims to be used as an evaluation to get the fastest acceleration time by using cut and crashing method. From the data obtained fromthe time schedule, cost estimate plan (RAB),wage price analysis, and project materials,the next step is making the job network and determining the critical pathfor cut and crash method. The results of the study show that the project acceleration can be done up to 82 days or 7 days faster than the normal day, that is 89 days with acceleration cost of Rp. 347.935.000,00 or increased from the normal cost of Rp. 345.390.000,00. The percentage of the selected acceleration time ratio is approximately 6.02% faster than the normal time, while for the acceleration cost is approximately 0.68% greater than the normal cost. Therefore, with this research, the work actually can be completed on December 13, 2016.
项目解决延迟解决问题的替代方案(PUSKESMAS LAREN摄政案例研究)
能否按时完成建设项目是业主和承包商最重要的目标之一。一般来说,每一个建设项目都有具体的实施计划和实施进度。它包含了一些重要的东西,例如项目应该何时开始,何时完成,以及如何提供资源。如2016年拉蒙安县拉伦区公共卫生中心大楼开发项目,该项目被推迟了长达6周,导致规划进度和开发实施不准确。本研究的目的是为了评估采用切割碰撞法获得最快的加速时间。根据从时间计划、成本估算计划(RAB)、工资价格分析和项目材料中获得的数据,下一步是制作作业网络并确定切割和碰撞方法的关键路径。研究结果表明,项目加速最多可完成82天或比正常一天快7天,即89天,加速成本为347.93.5万卢比或比正常成本345.39万卢比增加。所选择的加速时间比的百分比比正常时间快约6.02%,而加速成本比正常成本高约0.68%。因此,通过这项研究,这项工作实际上可以在2016年12月13日完成。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信