{"title":"Holistic Cycle Time Analysis and Improvement Project within a 200mm Lithography I-line Production Area","authors":"T. Zarbock, F. Lehmann, J. Fellendorf","doi":"10.1109/ASMC.2006.1638736","DOIUrl":null,"url":null,"abstract":"In this paper, a holistic approach for analyzing and improving a work center's performance focusing on cycle time improvement is described. We give an insight into the setup and execution of the project as well as achieved results and success factors. Also, lessons learned within this project are shared","PeriodicalId":407645,"journal":{"name":"The 17th Annual SEMI/IEEE ASMC 2006 Conference","volume":"25 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2006-05-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"The 17th Annual SEMI/IEEE ASMC 2006 Conference","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ASMC.2006.1638736","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
In this paper, a holistic approach for analyzing and improving a work center's performance focusing on cycle time improvement is described. We give an insight into the setup and execution of the project as well as achieved results and success factors. Also, lessons learned within this project are shared