Pengaruh Geometri Jalan Tambang Terhadap Alat Angkut Kegiatan Pengupasan Overburden Penambangan Batubara PT Tata Bara Utama di Kabupaten Bayung Lencir, Provinsi Sumatera Selatan
{"title":"Pengaruh Geometri Jalan Tambang Terhadap Alat Angkut Kegiatan Pengupasan Overburden Penambangan Batubara PT Tata Bara Utama di Kabupaten Bayung Lencir, Provinsi Sumatera Selatan","authors":"Nabil Zulfa Maulana, Zaenal, I. Wijaksana","doi":"10.29313/bcsme.v2i2.4372","DOIUrl":null,"url":null,"abstract":"Abstract. PT Tata Bara Utama is a contractor from PT Manggala Alam Lestari which is saved to overcome Over Burden (OB) with a target of reaching 288,200 BCM in one month. The company's production target was not achieved due to unfavorable road geometry conditions. This is because there are several mine road geometries that do not meet the standards of Ministerial Decree 1827 k/30/m/2018, thus hampering the production of conveyances. The conveyance used is the 745 articular dump truck. The conveyance operates from the front of the work to the disposal with a distance of 2700 m. Productivity of hauling equipment is strongly influenced by the geometry of the mine road, so that the 13 segments of the mine road geometry do not meet the standards of Kepmen 1827 and must be repaired immediately. In the results of the study, there were several segments of the mining road that were not in accordance with these standards. There are 3 segments on the straight road and 5 segments on the bend road that do not meet the standards in the geometry of the mining road, but the grade (slope of the road) has met the standards of Kepmen 1827, and there are still some segments of the embankment that do not meet these standards. This means that the productivity produced in each unit of conveyance is 49.67 BCM/hour so that the production of PT Tata Bara Utama reaches 196,700 BCM/Month while the production target is 288,200 BCM, so the production target is not achieved. Therefore, it is necessary to do reconstruction so that the desired production target of the company will be achieved. This means that the greater the cycle time value on the conveyance, the lower the productivity so that production is not reached. \nAbstrak. PT Tata Bara Utama merupakan perusahaan kontraktor dari PT Manggala Alam Lestari yang bertugas untuk mengupas Over Burden (OB) dengan target mencapai 288.200 BCM dalam satu bulan. Target produksi perusahaan tidak tercapai dikarenakan kondisi geometri jalan yang tidak mendukung. Hal ini terdapat beberapa geometri jalan tambang belum memenuhi standar Kepmen 1827 k/30/m/2018 sehingga menghambat kerja produksi alat angkut. Alat angkut yang digunakan yaitu articular dump truck 745. Alat angkut beroperasi dari front kerja menuju disposal dengan jarak 2700 m. Produktivitas alat angkut sangat dipengaruhi oleh geometri jalan tambang, sehingga dari 13 segmen geometri jalan tambang belum memenuhi standar Kepmen 1827 dan harus segera diperbaiki. Pada hasil penelitian terdapat beberapa segmen jalan tambang yang belum sesuai dengan standar tersebut. Ada 3 segmen pada jalan lurus dan ada 5 segmen pada jalan belokan yang belum memenuhi standar pada geometri jalan tambang, akan tetapi grade (kemiringan jalan) telah memenuhi standar Kepmen 1827, dan tanggul masih ada beberapa segmen yang belum memenuhi standar tersebut. Hal ini produktivitas yang dihasilkan pada tiap unit alat angkut sebesar 49,67 BCM/jam sehingga produksi PT Tata Bara Utama mencapai 196,700 BCM/Bulan sedangkan target produksi 288.200 BCM maka target produksi tidak tercapai. Maka dari itu perlu dilakukan rekontruksi agar target produksi yang diinginkan perusahaan akan tercapai. Hal ini semakin besar nilai cycle time pada alat angkut akan semakin kecil produktivitasnya sehingga produksi tidak tercapai.","PeriodicalId":187584,"journal":{"name":"Bandung Conference Series: Mining Engineering","volume":"15 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Bandung Conference Series: Mining Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29313/bcsme.v2i2.4372","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
Abstract. PT Tata Bara Utama is a contractor from PT Manggala Alam Lestari which is saved to overcome Over Burden (OB) with a target of reaching 288,200 BCM in one month. The company's production target was not achieved due to unfavorable road geometry conditions. This is because there are several mine road geometries that do not meet the standards of Ministerial Decree 1827 k/30/m/2018, thus hampering the production of conveyances. The conveyance used is the 745 articular dump truck. The conveyance operates from the front of the work to the disposal with a distance of 2700 m. Productivity of hauling equipment is strongly influenced by the geometry of the mine road, so that the 13 segments of the mine road geometry do not meet the standards of Kepmen 1827 and must be repaired immediately. In the results of the study, there were several segments of the mining road that were not in accordance with these standards. There are 3 segments on the straight road and 5 segments on the bend road that do not meet the standards in the geometry of the mining road, but the grade (slope of the road) has met the standards of Kepmen 1827, and there are still some segments of the embankment that do not meet these standards. This means that the productivity produced in each unit of conveyance is 49.67 BCM/hour so that the production of PT Tata Bara Utama reaches 196,700 BCM/Month while the production target is 288,200 BCM, so the production target is not achieved. Therefore, it is necessary to do reconstruction so that the desired production target of the company will be achieved. This means that the greater the cycle time value on the conveyance, the lower the productivity so that production is not reached.
Abstrak. PT Tata Bara Utama merupakan perusahaan kontraktor dari PT Manggala Alam Lestari yang bertugas untuk mengupas Over Burden (OB) dengan target mencapai 288.200 BCM dalam satu bulan. Target produksi perusahaan tidak tercapai dikarenakan kondisi geometri jalan yang tidak mendukung. Hal ini terdapat beberapa geometri jalan tambang belum memenuhi standar Kepmen 1827 k/30/m/2018 sehingga menghambat kerja produksi alat angkut. Alat angkut yang digunakan yaitu articular dump truck 745. Alat angkut beroperasi dari front kerja menuju disposal dengan jarak 2700 m. Produktivitas alat angkut sangat dipengaruhi oleh geometri jalan tambang, sehingga dari 13 segmen geometri jalan tambang belum memenuhi standar Kepmen 1827 dan harus segera diperbaiki. Pada hasil penelitian terdapat beberapa segmen jalan tambang yang belum sesuai dengan standar tersebut. Ada 3 segmen pada jalan lurus dan ada 5 segmen pada jalan belokan yang belum memenuhi standar pada geometri jalan tambang, akan tetapi grade (kemiringan jalan) telah memenuhi standar Kepmen 1827, dan tanggul masih ada beberapa segmen yang belum memenuhi standar tersebut. Hal ini produktivitas yang dihasilkan pada tiap unit alat angkut sebesar 49,67 BCM/jam sehingga produksi PT Tata Bara Utama mencapai 196,700 BCM/Bulan sedangkan target produksi 288.200 BCM maka target produksi tidak tercapai. Maka dari itu perlu dilakukan rekontruksi agar target produksi yang diinginkan perusahaan akan tercapai. Hal ini semakin besar nilai cycle time pada alat angkut akan semakin kecil produktivitasnya sehingga produksi tidak tercapai.
摘要。PT Tata Bara Utama是PT Manggala Alam Lestari的承包商,该公司是为了克服过度负担而节省下来的,目标是在一个月内达到288,200亿立方米。由于不利的道路几何条件,该公司的生产目标未能实现。这是因为有几条矿山道路的几何形状不符合第1827 k/30/m/2018号部长级法令的标准,从而阻碍了运输工具的生产。使用的运输工具是745铰接式自卸卡车。运输工具从作业前到处置处的距离为2700米。拖运设备的生产率受矿山道路几何形状的强烈影响,导致矿山道路几何形状有13段不符合Kepmen 1827的标准,必须立即修复。在研究结果中,有几段采矿道路不符合这些标准。矿山道路几何形状不符合标准的直道有3段,弯道有5段,但坡度(道路坡度)达到了Kepmen 1827的标准,还有部分路堤路段不符合这些标准。这意味着每个运输单元的生产率为49.67 BCM/小时,因此PT Tata Bara Utama的产量达到196,700 BCM/月,而生产目标为288,200 BCM,因此生产目标没有实现。因此,有必要进行改造,以达到公司预期的生产目标。这意味着输送的周期时间值越大,生产力就越低,因此无法达到生产。Abstrak。Tata Bara Utama merupakan perushaan kontraktor dari PT Manggala Alam Lestari yang bertugas untuk mengupas Over Burden (OB)登根目标menapai 288200 BCM dalam satu bulan。目标产品为perusahaan tidak tercapai dikarenakan kondisi geometri jalan yang tidak mendukung。Hal ini terdapat beberapa geometri jalan tambang belum memuhi standard kemmen 1827 k/30/m/2018 sehinga menghambat kerja producksi alat angkut。Alat angkut yang digunakan yitu关节自卸卡车745。Alat angkut beroperasi dari front kerja menuju disposal dengan jarak 2700米。生产活动为alat angkut sangat dipengaruhi oleh geometri jalan tambang, seingga dari, 13段geometri jalan tambang belum memuhi标准Kepmen 1827 dan harus segera diperbaiki。Pada hasil penelitian terdapat beberapa segmen jalan tambang yang belum sesuai dengan标准序列。阿达3段阿达jalan lurus丹达5段阿达jalan belokan yang belum memenuhi标准阿达几何阿达jalan tambang,阿达tetapi等级(kemiringan jalan) telah memenuhi标准Kepmen 1827,丹tanggul masih阿达beberapa segmen yang belenuhi标准tersebut。哈尔尼的生产活动,杨迪哈西坎帕达达达装置,安库特sebesar 49,67 BCM/jam seingga产品PT塔塔巴拉乌塔玛曼达196,700 BCM/Bulan sedangkan目标产品288,200 BCM maka目标产品达达装置。Maka dari itu perlu dilakukan rekontruksi琼脂靶产品,是一种新型的琼脂靶产品。Hal - ini semakin是一种新型的周期时间模型,它可以使生产效率提高,并使生产效率提高。