{"title":"An Algorithm to Minimize Maximum Job Lateness and Flowtime in Two-Machine System","authors":"T. Sen, B. N. Borah, O. Foong","doi":"10.1109/SSST.1992.712258","DOIUrl":null,"url":null,"abstract":"This paper considers the dual criteria of minimizing flowtime and maximum lateness of jobs in the two-machine flowshop system. We discover the conditions that determine which of a pair of adjacent jobs in a sequence should precede the other to minimize either of the two objective functions. We also present a Branch-and-Bound solution procedure to arrive at an optimal solution.","PeriodicalId":359363,"journal":{"name":"The 24th Southeastern Symposium on and The 3rd Annual Symposium on Communications, Signal Processing Expert Systems, and ASIC VLSI Design System Theory","volume":"165 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1992-03-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"The 24th Southeastern Symposium on and The 3rd Annual Symposium on Communications, Signal Processing Expert Systems, and ASIC VLSI Design System Theory","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/SSST.1992.712258","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
This paper considers the dual criteria of minimizing flowtime and maximum lateness of jobs in the two-machine flowshop system. We discover the conditions that determine which of a pair of adjacent jobs in a sequence should precede the other to minimize either of the two objective functions. We also present a Branch-and-Bound solution procedure to arrive at an optimal solution.