Simulations of the Crude Oil Tank Refurbishment Project Risks Using Monte Carlo

A. Sandhyavitri, Arvin Arvin, F. Restuhadi
{"title":"Simulations of the Crude Oil Tank Refurbishment Project Risks Using Monte Carlo","authors":"A. Sandhyavitri, Arvin Arvin, F. Restuhadi","doi":"10.31258/jamt.3.1.22-29","DOIUrl":null,"url":null,"abstract":"Simulation technology has assisted project stakeholders in predicting a range of the project results in the future under risks and uncertainties. The objectives of this article are to improve a comprehensive project planning in the perspective of the project scheduling by conducting simulations for the refurbishment of crude oil tank project risks using Monte Carlo simulations. The practical approaches for simulating the risks encompassed 3 stages: risk identification, assessment, and risk analysis using the Monte Carlo simulations. The implementation of Monte Carlo simulation in the form of stochastic approach however were not new, but the application of these approaches in the area of oil industrial projects was challenging. A Free Water Knock-Out (FWKO) tank project located in Duri, Indonesia was taken as a case study. The initial FWKO project duration was set up to be 180 working days, and it was delayed (up to 140% from the initial duration of the project planning). This study conducted deep questioner surveys from 25 oil industry stakeholders. It was identified 29 risk factors have been considered as the major causes of the project delay. The risk factors were then calculated qualitatively for performing risk indexes.  Based on the risk simulations (after 1000 iterations) using Monte Carlo simulations utilizing @risk application package (under uncertainties) there was found that the possibility of this project would  experience delays at the range of 47 days (126%) to 80 days (144%) from the initial project planning. This simulation had also identified the most sensitive activities causing project delays. The results was presented in the form of the spider graph diagram which assisted the project main stakeholders in developing a strategic decision during project planning phase.","PeriodicalId":287674,"journal":{"name":"Journal of Applied Materials and Technology","volume":"14 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-02-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Applied Materials and Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31258/jamt.3.1.22-29","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Simulation technology has assisted project stakeholders in predicting a range of the project results in the future under risks and uncertainties. The objectives of this article are to improve a comprehensive project planning in the perspective of the project scheduling by conducting simulations for the refurbishment of crude oil tank project risks using Monte Carlo simulations. The practical approaches for simulating the risks encompassed 3 stages: risk identification, assessment, and risk analysis using the Monte Carlo simulations. The implementation of Monte Carlo simulation in the form of stochastic approach however were not new, but the application of these approaches in the area of oil industrial projects was challenging. A Free Water Knock-Out (FWKO) tank project located in Duri, Indonesia was taken as a case study. The initial FWKO project duration was set up to be 180 working days, and it was delayed (up to 140% from the initial duration of the project planning). This study conducted deep questioner surveys from 25 oil industry stakeholders. It was identified 29 risk factors have been considered as the major causes of the project delay. The risk factors were then calculated qualitatively for performing risk indexes.  Based on the risk simulations (after 1000 iterations) using Monte Carlo simulations utilizing @risk application package (under uncertainties) there was found that the possibility of this project would  experience delays at the range of 47 days (126%) to 80 days (144%) from the initial project planning. This simulation had also identified the most sensitive activities causing project delays. The results was presented in the form of the spider graph diagram which assisted the project main stakeholders in developing a strategic decision during project planning phase.
用蒙特卡罗方法模拟原油储罐翻新工程的风险
仿真技术可以帮助项目干系人预测未来项目在风险和不确定性下的一系列结果。本文的目的是利用蒙特卡罗模拟法对原油储罐改造项目风险进行模拟,从项目调度的角度完善综合项目规划。模拟风险的实际方法包括三个阶段:风险识别、评估和使用蒙特卡洛模拟的风险分析。以随机方法的形式实施蒙特卡罗模拟并不新鲜,但这些方法在石油工业项目领域的应用具有挑战性。以印度尼西亚Duri的一个免费水淘汰(FWKO)水箱项目为例进行研究。最初的FWKO项目工期设定为180个工作日,并被推迟(比项目规划的初始工期推迟了140%)。这项研究对25个石油行业的利益相关者进行了深入的调查。确定了29个风险因素,被认为是导致项目延期的主要原因。然后定性地计算风险因素以执行风险指数。基于风险模拟(在1000次迭代之后),使用蒙特卡罗模拟,利用@risk应用程序包(在不确定的情况下),发现这个项目从最初的项目计划开始,可能会经历47天(126%)到80天(144%)的延迟。该模拟还确定了导致项目延误的最敏感活动。结果以蜘蛛图的形式呈现,帮助项目主要利益相关者在项目规划阶段制定战略决策。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信