Research of Hydropower Stations Optimal Operation Based on the Discrete Differential Dynamic Programming - Progressive Optimization Algorithm Combination Method
{"title":"Research of Hydropower Stations Optimal Operation Based on the Discrete Differential Dynamic Programming - Progressive Optimization Algorithm Combination Method","authors":"Xuan Yingji, Mei Yadong, Xu Jiangsong","doi":"10.1109/SERA.2009.26","DOIUrl":null,"url":null,"abstract":"The progressive optimization algorithm over-depends on the initial state, it needs to assume certain different types of initial test strategies and corresponding initial test paths, the calculation process repeats 2 to 5 times. Considering the shortfalls mentioned above, this paper presents discrete differential dynamic programming-progressive optimum combination method which is applied in the operation of hydropower station and designs a solution based on the method to optimize the operation of hydropower stations. Calculation example shows that this method is effective, highly reliable in global optimization and full of prospects.","PeriodicalId":333607,"journal":{"name":"2009 Seventh ACIS International Conference on Software Engineering Research, Management and Applications","volume":"20 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2009-12-02","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"7","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2009 Seventh ACIS International Conference on Software Engineering Research, Management and Applications","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/SERA.2009.26","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 7
Abstract
The progressive optimization algorithm over-depends on the initial state, it needs to assume certain different types of initial test strategies and corresponding initial test paths, the calculation process repeats 2 to 5 times. Considering the shortfalls mentioned above, this paper presents discrete differential dynamic programming-progressive optimum combination method which is applied in the operation of hydropower station and designs a solution based on the method to optimize the operation of hydropower stations. Calculation example shows that this method is effective, highly reliable in global optimization and full of prospects.