Using Budgeted Cost of Work Performed to Predict Estimates at Completion for Mid-Acquisition Space Programs

C. Keaton
{"title":"Using Budgeted Cost of Work Performed to Predict Estimates at Completion for Mid-Acquisition Space Programs","authors":"C. Keaton","doi":"10.1080/1941658X.2015.1016585","DOIUrl":null,"url":null,"abstract":"Conventional techniques to predict estimates at completion using earned value management data generally underpredict the end costs for space acquisition programs. This research assesses the accuracies of earned value management analysis methods to forecast estimates at completion for on-going space system acquisitions. The identification of more accurate “mid-stream” earned value management analysis methods improves managers’ abilities to assess the reasonableness of cost estimates. This research finds the linear relationship between budgeted cost of work performed and time yields a more accurate earned value management-based prediction for space program estimates at completion than existing methods. This result offers an empirically-supported method for earned value management data that may be useful to cost analysts and managers alike.","PeriodicalId":390877,"journal":{"name":"Journal of Cost Analysis and Parametrics","volume":"239 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2015-01-02","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Cost Analysis and Parametrics","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1080/1941658X.2015.1016585","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

Abstract

Conventional techniques to predict estimates at completion using earned value management data generally underpredict the end costs for space acquisition programs. This research assesses the accuracies of earned value management analysis methods to forecast estimates at completion for on-going space system acquisitions. The identification of more accurate “mid-stream” earned value management analysis methods improves managers’ abilities to assess the reasonableness of cost estimates. This research finds the linear relationship between budgeted cost of work performed and time yields a more accurate earned value management-based prediction for space program estimates at completion than existing methods. This result offers an empirically-supported method for earned value management data that may be useful to cost analysts and managers alike.
使用已完成工作的预算成本来预测中期采办空间项目的完成预算
利用挣值管理数据预测完井估算的传统技术通常会低估空间采办项目的最终成本。本研究评估了挣值管理分析方法的准确性,以预测正在进行的空间系统采办的完成预算。更准确的“中游”挣值管理分析方法的识别提高了管理者评估成本估算合理性的能力。本研究发现,预算工作成本与时间之间的线性关系比现有方法更能准确地预测空间计划完成时的挣值管理。这一结果为挣值管理数据提供了一种经验支持的方法,可能对成本分析师和经理都很有用。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信