S. Galantino, Ilaria Colucci, R. Vignoli, A. S. Nyirenda
{"title":"Voltage Collapse Assessment in Developing Countries EHV Cross-Boundary Interconnection: A Case Study","authors":"S. Galantino, Ilaria Colucci, R. Vignoli, A. S. Nyirenda","doi":"10.1109/efea.2018.8617088","DOIUrl":null,"url":null,"abstract":"The development of the Lufubu Hydropower Cascade Project in Zambia comprises three cascade plants totalling 326 MW (Phase 2). The project is being promoted by the Lufubu Power Company (LPC) a private Zambian company which, with the support of consulting engineers Studio Pietrangeli (SP) that developed the design and the environmental and social impact assessments (ESIA), and the transaction advisors Fieldstone South Africa. The paper presents the main technical features of the project, its interconnection to the national grid as well as methodology and results of the voltage stability analysis, performed in CYME PSAF environment, of the Zambian power system with the target year 2030. The study is part of the feasibility design for the Lufubu Hydropower Cascade project development, carried out by SP, with the scope of assessing system operation behaviour synchronously interconnected with the neighbouring countries as the DR Congo, Tanzania, Malawi, Mozambique, Namibia, Angola, Zimbabwe and within the South African Power Pool (SAPP).","PeriodicalId":447143,"journal":{"name":"2018 5th International Symposium on Environment-Friendly Energies and Applications (EFEA)","volume":"2 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2018 5th International Symposium on Environment-Friendly Energies and Applications (EFEA)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/efea.2018.8617088","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
The development of the Lufubu Hydropower Cascade Project in Zambia comprises three cascade plants totalling 326 MW (Phase 2). The project is being promoted by the Lufubu Power Company (LPC) a private Zambian company which, with the support of consulting engineers Studio Pietrangeli (SP) that developed the design and the environmental and social impact assessments (ESIA), and the transaction advisors Fieldstone South Africa. The paper presents the main technical features of the project, its interconnection to the national grid as well as methodology and results of the voltage stability analysis, performed in CYME PSAF environment, of the Zambian power system with the target year 2030. The study is part of the feasibility design for the Lufubu Hydropower Cascade project development, carried out by SP, with the scope of assessing system operation behaviour synchronously interconnected with the neighbouring countries as the DR Congo, Tanzania, Malawi, Mozambique, Namibia, Angola, Zimbabwe and within the South African Power Pool (SAPP).
赞比亚卢富布水电站梯级项目的开发包括三个总计326兆瓦的梯级电厂(第二期)。该项目由卢富布电力公司(LPC)推动,该公司是一家赞比亚私营公司,在开发设计和环境与社会影响评估(ESIA)的咨询工程师工作室Pietrangeli (SP)和交易顾问公司Fieldstone South Africa的支持下。本文介绍了该项目的主要技术特点,它与国家电网的互联,以及在CYME PSAF环境下对赞比亚电力系统进行的电压稳定性分析的方法和结果,目标是2030年。该研究是卢富布水电站梯级项目开发可行性设计的一部分,由SP公司开展,评估系统运行行为的范围与刚果民主共和国、坦桑尼亚、马拉维、莫桑比克、纳米比亚、安哥拉、津巴布韦等邻国以及南非电力联营(SAPP)内同步互联。