Lifting Work Process Optimization Method in High-rise Building Construction Through Improvement of CYCLONE Modeling Method

Doowon Hawng, O-K. Kwon, Yoon-Ki Choi
{"title":"Lifting Work Process Optimization Method in High-rise Building Construction Through Improvement of CYCLONE Modeling Method","authors":"Doowon Hawng, O-K. Kwon, Yoon-Ki Choi","doi":"10.6106/kjcem.2017.18.2.058","DOIUrl":null,"url":null,"abstract":"The planning for material lifting operations is one of the key processes in high-rise building construction. Several previous studies have used rough calculations by referring to existing practices or establishing a target value for lifting cycle time or operating rate. Therefore, the purpose of this study is to propose a material lifting process optimization method for reducing the lifting cycle time and increasing the operating rate. In this study, we improve the cyclic operation network (CYCLONE) modeling method that considers the duration and zone information of each work task. This method can be used to hand over work tasks to another crew group in the work process. According to this methodology, this study optimizes the material lifting process, performs a sensitivity analysis, and evaluates the field applicability of the proposed material lifting process optimization method. Therefore, the optimized process was then applied to a high-rise building construction site. The lifting work process time and operating rate for the simulated asis lifting process data, optimized process data, and field application result data were compared for each lifting height. From this comparison, the effectiveness of the optimization methodology was confirmed.","PeriodicalId":220018,"journal":{"name":"Korean Journal of Construction Engineering and Management","volume":"38 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2017-03-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Korean Journal of Construction Engineering and Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.6106/kjcem.2017.18.2.058","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

Abstract

The planning for material lifting operations is one of the key processes in high-rise building construction. Several previous studies have used rough calculations by referring to existing practices or establishing a target value for lifting cycle time or operating rate. Therefore, the purpose of this study is to propose a material lifting process optimization method for reducing the lifting cycle time and increasing the operating rate. In this study, we improve the cyclic operation network (CYCLONE) modeling method that considers the duration and zone information of each work task. This method can be used to hand over work tasks to another crew group in the work process. According to this methodology, this study optimizes the material lifting process, performs a sensitivity analysis, and evaluates the field applicability of the proposed material lifting process optimization method. Therefore, the optimized process was then applied to a high-rise building construction site. The lifting work process time and operating rate for the simulated asis lifting process data, optimized process data, and field application result data were compared for each lifting height. From this comparison, the effectiveness of the optimization methodology was confirmed.
基于旋风建模方法改进的高层建筑施工吊装工序优化方法
材料起重作业的规划是高层建筑施工的关键环节之一。以前的一些研究通过参考现有实践或建立举升周期时间或开工率的目标值来进行粗略计算。因此,本研究的目的是提出一种缩短吊运周期时间,提高运转率的物料吊运工艺优化方法。在本研究中,我们改进了循环运行网络(CYCLONE)建模方法,该方法考虑了每个工作任务的持续时间和区域信息。这种方法可以用于在工作过程中将工作任务移交给另一个小组。根据该方法对物料提升过程进行优化,进行敏感性分析,并对所提出的物料提升过程优化方法的现场适用性进行评价。因此,将优化后的工艺应用于某高层建筑施工现场。比较了各提升高度下模拟提升工艺数据、优化工艺数据和现场应用结果数据的提升作业时间和开工率。通过比较,验证了优化方法的有效性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信