Early assessment of grid code requirements for wind power plant in vestas

Y. Zhan, P. Zhao
{"title":"Early assessment of grid code requirements for wind power plant in vestas","authors":"Y. Zhan, P. Zhao","doi":"10.1109/IPEC.2010.5543449","DOIUrl":null,"url":null,"abstract":"Grid code requirements on wind power plant are becoming more stringent as the wind power penetration level increasing. In order to identify the risk of incompliance with grid code requirements at the planning stage of a wind power plant project, a standard grid code study process has been established in Vestas. The study process includes steady state load flow, short circuit studies and transient low voltage ride through study. A suitable reactive power compensation device is identified from the study. An example study case is also included in this paper.","PeriodicalId":353540,"journal":{"name":"The 2010 International Power Electronics Conference - ECCE ASIA -","volume":"68 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2010-06-21","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"The 2010 International Power Electronics Conference - ECCE ASIA -","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/IPEC.2010.5543449","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

Grid code requirements on wind power plant are becoming more stringent as the wind power penetration level increasing. In order to identify the risk of incompliance with grid code requirements at the planning stage of a wind power plant project, a standard grid code study process has been established in Vestas. The study process includes steady state load flow, short circuit studies and transient low voltage ride through study. A suitable reactive power compensation device is identified from the study. An example study case is also included in this paper.
维斯塔斯风力发电厂电网规范要求的早期评估
随着风电渗透水平的提高,电网规范对风电场的要求也越来越严格。为了识别风电场项目规划阶段不符合电网规范要求的风险,维斯塔斯建立了标准的电网规范研究流程。研究过程包括稳态潮流研究、短路研究和瞬态低压穿越研究。通过研究确定了合适的无功补偿装置。本文还提供了一个实例研究案例。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信