{"title":"Determining Ground Insulation Parameters in Quarry Distribution Networks of Mining Companies in Tajikistan","authors":"K. Boboev, A. Sidorov, O. Khanzhina","doi":"10.1109/UralCon49858.2020.9216311","DOIUrl":null,"url":null,"abstract":"The article deals with the brief description of mining companies in the Republic of Tajikistan (RT) and isolation levels of 6 kV quarry distribution networks. The specified network isolation parameters relative to the earth were determined by calculations based on the methods developed at the Department of “Life safety”, South Ural State University (SUSU). Calculations of insulation relative to the ground in quarry distribution electric networks of mining companies in the Republic of Tajikistan have shown that the value of capacitance currents of single-phase earth fault lies within 0.1 A to 0.37 A and depends on development levels of the companies. The active insulation resistances of the network phases relative to the ground are in the range from 18 k k Ω to 112 k Ω, considering the change in the network quiescence coefficient. The network capacity relative to the ground is in the range from 0.09 µF to 0.34 µF. The data obtained is necessary for selecting a security tool and evaluating the level of security.","PeriodicalId":230353,"journal":{"name":"2020 International Ural Conference on Electrical Power Engineering (UralCon)","volume":"331 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2020 International Ural Conference on Electrical Power Engineering (UralCon)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/UralCon49858.2020.9216311","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1
Abstract
The article deals with the brief description of mining companies in the Republic of Tajikistan (RT) and isolation levels of 6 kV quarry distribution networks. The specified network isolation parameters relative to the earth were determined by calculations based on the methods developed at the Department of “Life safety”, South Ural State University (SUSU). Calculations of insulation relative to the ground in quarry distribution electric networks of mining companies in the Republic of Tajikistan have shown that the value of capacitance currents of single-phase earth fault lies within 0.1 A to 0.37 A and depends on development levels of the companies. The active insulation resistances of the network phases relative to the ground are in the range from 18 k k Ω to 112 k Ω, considering the change in the network quiescence coefficient. The network capacity relative to the ground is in the range from 0.09 µF to 0.34 µF. The data obtained is necessary for selecting a security tool and evaluating the level of security.
本文简要介绍了塔吉克斯坦共和国(RT)的矿业公司和6千伏采石场配电网络的隔离水平。根据南乌拉尔国立大学(SUSU)“生命安全”系开发的方法,通过计算确定了相对于地球的特定网络隔离参数。塔吉克斯坦矿业公司采石场配电网的接地绝缘计算表明,单相接地故障的电容电流值在0.1 ~ 0.37 A之间,这取决于公司的发展水平。考虑到网络静息系数的变化,网络相相对于地的主动绝缘电阻在18 k k Ω ~ 112 k Ω之间。网络相对于地的容量范围为0.09µF ~ 0.34µF。获得的数据对于选择安全工具和评估安全级别是必要的。