Assessment of Delay Factors and its Impacts on Selected Road Construction Supervised by Department of Road

Bhawani Dhakal
{"title":"Assessment of Delay Factors and its Impacts on Selected Road Construction Supervised by Department of Road","authors":"Bhawani Dhakal","doi":"10.24321/2456.9925.202104","DOIUrl":null,"url":null,"abstract":"The objective of the study was to analyze the factors causing delay, their impacts, and the perception of local stakeholder towards the delay caused by delay causing factors. Questionnaire surveys were conducted and examination of records from concerned stakeholders within the research area has been carried out. The factors affecting the project delay were ranked using ‘five-point’ scale ranged from 1 (strongly disagree) to 5 (strongly agree) and transformed to Relative Importance Index (RII). This study was carried out on the basis of literature review and the questionnaire survey on selected road to know the opinion of different parties involved. The questionnaire contained questions on delay causing factors identified through literature review and it came to eight groups and its impacts to five groups and perceptions of local stakeholder towards the delay caused by these delay factors into three groups on three roads i.e. Bharatpur-Meghauli road, Bharatpur-Bypass road, Baseni-Padampur road in Bharatpur Metropolitan City. The top five delay factors identified through the analysis of RII were political interference by political parties, timely payment to labors, local and political pressure, financial problem of the contractor and poor communication of consultant with other working parties. External factor was found to be the ranked one delay causing factors followed by labor factor, project factor, contractor factor and consultant factor. Time overrun cost overrun, wastages and under-utilization of human resources, cost inflation for equipment and materials due to extension of time and reputation of all parties’ involved in the projects were the impacts of delays. The SPI for all three roads was found less than 1 indicating all three projects were behind the schedule (time overrun). For the perception of local stakeholder towards the delay on road construction: accident on site, price inflation in goods and services, increase in noise pollution, increased in air pollution due to dust and particulates and human health were the top most main perceptions.","PeriodicalId":267306,"journal":{"name":"Journal of Advanced Research in Construction and Urban Architecture","volume":"31 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-05-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Advanced Research in Construction and Urban Architecture","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24321/2456.9925.202104","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The objective of the study was to analyze the factors causing delay, their impacts, and the perception of local stakeholder towards the delay caused by delay causing factors. Questionnaire surveys were conducted and examination of records from concerned stakeholders within the research area has been carried out. The factors affecting the project delay were ranked using ‘five-point’ scale ranged from 1 (strongly disagree) to 5 (strongly agree) and transformed to Relative Importance Index (RII). This study was carried out on the basis of literature review and the questionnaire survey on selected road to know the opinion of different parties involved. The questionnaire contained questions on delay causing factors identified through literature review and it came to eight groups and its impacts to five groups and perceptions of local stakeholder towards the delay caused by these delay factors into three groups on three roads i.e. Bharatpur-Meghauli road, Bharatpur-Bypass road, Baseni-Padampur road in Bharatpur Metropolitan City. The top five delay factors identified through the analysis of RII were political interference by political parties, timely payment to labors, local and political pressure, financial problem of the contractor and poor communication of consultant with other working parties. External factor was found to be the ranked one delay causing factors followed by labor factor, project factor, contractor factor and consultant factor. Time overrun cost overrun, wastages and under-utilization of human resources, cost inflation for equipment and materials due to extension of time and reputation of all parties’ involved in the projects were the impacts of delays. The SPI for all three roads was found less than 1 indicating all three projects were behind the schedule (time overrun). For the perception of local stakeholder towards the delay on road construction: accident on site, price inflation in goods and services, increase in noise pollution, increased in air pollution due to dust and particulates and human health were the top most main perceptions.
路政部门监理选定道路施工延误因素评价及其影响
本研究的目的是分析造成延误的因素及其影响,以及当地利益相关者对延误因素造成的延误的看法。进行了问卷调查,并审查了研究领域内有关利益相关者的记录。影响项目延迟的因素使用“五分制”进行排名,范围从1(非常不同意)到5(非常同意),并转换为相对重要性指数(RII)。本研究是在文献综述的基础上,在选定的道路上进行问卷调查,以了解各方的意见。问卷包含了通过文献综述确定的延误导致因素的问题,它分为八个组及其对五个组的影响,以及当地利益相关者对这些延误因素造成的延误的看法,分为三个组,即巴拉特普尔-梅戈里路,巴拉特普尔-绕行路,巴塞尼-帕丹普尔路在巴拉特普尔大都市。通过RII分析确定的前五大延迟因素是政党的政治干预、及时支付劳工、地方和政治压力、承包商的财务问题以及顾问与其他工作组沟通不周。外部因素是造成延误的主要因素,其次是劳动力因素、项目因素、承包商因素和顾问因素。时间超支、成本超支、人力资源的浪费和利用不足、由于时间和项目各方声誉的延长而导致的设备和材料成本膨胀是延误的影响。所有三条道路的SPI都小于1,这表明所有三个项目都落后于计划(超时)。对于当地利益相关者对道路建设延误的看法:现场事故、商品和服务价格上涨、噪音污染增加、灰尘和微粒造成的空气污染增加以及人类健康是最主要的看法。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信