Construction Duration Prediction Model of Power Transmission and Transformation Project Based on BP Neural Network

Bo Yu, Xiaomin Liu, Xinrui Ju, Ye Wan, Yuanyuan Liu
{"title":"Construction Duration Prediction Model of Power Transmission and Transformation Project Based on BP Neural Network","authors":"Bo Yu, Xiaomin Liu, Xinrui Ju, Ye Wan, Yuanyuan Liu","doi":"10.23919/WAC55640.2022.9934292","DOIUrl":null,"url":null,"abstract":"There are many factors affecting the total construction duration of power transmission and transformation project, resulting in low accuracy of construction duration prediction. And the traditional construction duration prediction method has some limitations to a certain extent. The prediction results mainly rely on historical information materials and expert judgment, so it has always been the difficulty of prediction. Aiming at the existing problems, a total construction duration prediction method of power transmission and transformation project based on BP neural network theory is proposed. The theory has high generalization ability and the ability to solve nonlinear influencing factors, which can greatly improve the accuracy of construction duration prediction.","PeriodicalId":339737,"journal":{"name":"2022 World Automation Congress (WAC)","volume":"32 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-10-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2022 World Automation Congress (WAC)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.23919/WAC55640.2022.9934292","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

There are many factors affecting the total construction duration of power transmission and transformation project, resulting in low accuracy of construction duration prediction. And the traditional construction duration prediction method has some limitations to a certain extent. The prediction results mainly rely on historical information materials and expert judgment, so it has always been the difficulty of prediction. Aiming at the existing problems, a total construction duration prediction method of power transmission and transformation project based on BP neural network theory is proposed. The theory has high generalization ability and the ability to solve nonlinear influencing factors, which can greatly improve the accuracy of construction duration prediction.
基于BP神经网络的输变电工程工期预测模型
输变电工程总工期影响因素较多,导致工期预测精度较低。传统的工期预测方法存在一定的局限性。预测结果主要依赖于历史信息材料和专家判断,因此一直是预测的难点。针对存在的问题,提出了一种基于BP神经网络理论的输变电工程总工期预测方法。该理论具有较高的泛化能力和求解非线性影响因素的能力,可大大提高工程工期预测的精度。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信